Installing two sorting and wash lines, a water treatment plant and three Erema extruders for a UK recycling plant.

Mechanical and electrical installation for a UK plastic recycling plant

United Kingdom

Integrating recycling process equipment and services across a long-running installation programme

Our UK team was appointed by a blue-chip plastics company to carry out the mechanical and electrical installation of a plastic recycling plant, working closely with two original equipment manufacturers. The plant combined sorting, washing, water treatment and extrusion equipment. The published project update documented more than 20 months of delivery.


Equipment assembly, line levelling and utility integration across the recycling plant

The mechanical and electrical installation scope began with offloading and centre-line marking, then moved through equipment assembly, line levelling and connection of site services. Two plastic recycling sorting and wash lines were installed alongside a water treatment plant and three Erema extruder machines with silos. The team also installed electrical services, compressed air and process water needed by the production equipment.

Offloading and centre-line marking for incoming equipment
Installation of two plastic recycling sorting and wash lines
Installation of a water treatment plant
Installation of three Erema extruder machines and associated silos
Full equipment assembly and line levelling
Installation of electrical services, compressed air and process water
Offloading and centre-line marking for incoming equipment
Installation of two plastic recycling sorting and wash lines
Installation of a water treatment plant
Installation of three Erema extruder machines and associated silos
Full equipment assembly and line levelling
Installation of electrical services, compressed air and process water
Offloading and centre-line marking for incoming equipment
Installation of two plastic recycling sorting and wash lines
Installation of a water treatment plant
Installation of three Erema extruder machines and associated silos
Full equipment assembly and line levelling
Installation of electrical services, compressed air and process water
Offloading and centre-line marking for incoming equipment
Installation of two plastic recycling sorting and wash lines
Installation of a water treatment plant
Installation of three Erema extruder machines and associated silos
Full equipment assembly and line levelling
Installation of electrical services, compressed air and process water
  • Offloading and centre-line marking for incoming equipment
  • Installation of two plastic recycling sorting and wash lines
  • Installation of a water treatment plant
  • Installation of three Erema extruder machines and associated silos
  • Full equipment assembly and line levelling
  • Installation of electrical services, compressed air and process water

Principal recycling equipment installed during the documented programme

The published project update records more than 20 months of delivery. By that stage, the principal recycling equipment and associated services had been installed, while later project phases were continuing.

Sorting and wash lines
2
Erema extruders
3
Water treatment plant
1
Programme documented
20+ months

Need to know more?

What equipment did the recycling plant installation include?
Two plastic recycling sorting and wash lines, a water treatment plant and three Erema extruder machines with silos, together with the electrical services, compressed air and process water needed by the equipment.
Project Details
  • Client: Blue-chip plastics company
  • Location: United Kingdom
  • Sector: Other Industries
  • Programme: Mechanical and electrical plant installation
  • Timeline: 20+ months documented

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.