Machine relocation at Beck & Pollitzer covers the whole move: dismantling, match-marking, lifting, packing, transport, unloading, positioning and reinstallation. Our teams move individual machines, production cells and complete production lines within a facility, between sites or across borders.
Manufacturers such as Stellantis, Bosch and Procter & Gamble have used our teams for machine and production-line relocations, some of them between countries.
Each project is planned around the equipment, route, access constraints and production schedule. Dismantling sequences, specialist lifting, transport and destination-site readiness are coordinated through move planning and interface control, so the client works with one project team from first dismantling to final reinstallation.
Dismantling, moving and reinstallation
A machine move runs through four stages, each with its own technical and logistical requirements. Scope can follow a single asset or span several machines and production areas. Equipment that is being retired rather than moved falls under controlled removal and decommissioning.

Dismantling, match-marking & preparation
Before equipment is moved, our teams disconnect services, document assemblies and match-mark mechanical, electrical and piping components so the machine can be reassembled correctly. Dismantling methods are developed around the equipment, the access available and the lifting sequence.
- Mechanical and electrical disconnection
- Machine dismantling and strip-down
- Match-marking of components
- Photographic and written dismantling records
- Removal of floor fixings and ancillary structures
- Crating of sensitive components

Lifting, loading & internal movement
Machinery is moved from its operating position to the loading point using equipment selected for the asset weight, geometry and site constraints. This can include forklifts, VersaLifts, hydraulic gantries, cranes and specialist transport systems.
- Heavy machinery removal
- Internal machinery movement
- Rigging and controlled lifting
- Loading and unloading
- Restricted-access moves
- Lift planning for heavy equipment

Transport, packing & relocation logistics
Domestic and international moves need machinery, lifting equipment, packaging and transport resources sequenced around site access and production requirements. Where equipment cannot go straight from one site to the other, staged delivery and interim holding can bridge the gap.
- Machine transport services
- Packing for road, sea or storage
- Route and permit planning
- Vehicle and trailer selection
- Cross-border transport coordination
- Temporary storage and consolidation

Reinstallation, positioning & verification
At the destination, machinery is unloaded, positioned and reassembled ready for reconnection and commissioning support. Where the move requires dimensional checks, datum transfer or laser-based verification, our measurement and verification team can check positioning against project or OEM requirements.
- Equipment unloading and placement
- Mechanical reassembly
- Re-levelling at the destination
- Datum and alignment checks
- Utility reconnection support
- Pre-commissioning and handover support

Vulcanisation press relocation from Tunisia to the Czech Republic
- 450 Project hours
- 30 days Duration
- 2 Countries

Technical rigging & retrofit: integrating a Gigafactory with more than 3,500 assets
- 29,467 Project hours
- 117 days Duration
- 3,506 Items relocated

Multi-floor relocation of fragile printing equipment for a pharmaceutical manufacturer
- 8 Machines relocated
- 500 kg Heaviest unit
- 5,000 x 800 x 1,100 mm Largest units

Relocation of two pharmaceutical autoclaves in freezing outdoor conditions
- 2,500 kg Autoclave 1
- 850 kg Autoclave 2
- -2°C with snowfall Delivery conditions

Cross-border production cell relocation for a glass manufacturer
- 4 Dedicated trucks
- 2 Countries
- 0 Production delays

Production line relocation in Italy
- 2,900 Project hours
- 21 days Duration
- 12 On-site team

Cylinder head and block production line relocation: Poland to Brazil
- 50,000 Working hours
- 337 Trucks dispatched
- 2 Production lines relocated

Turnkey machinery relocation for an electrical components manufacturer
- 3,000 Project hours
- 5 operatives Core team
- match-marking through to reassembly Scope

Extrusion line and crystalliser move: Italy to Belgium
- 17 days Timeline
- 5 Trucks
- extrusion line, crystalliser and dosing units Equipment

Fuel injection pump production line move: Germany to Czech Republic
- 2 Production lines
- 30 Trucks
- 3-ton Forklifts
Wider machine relocation services
Industrial relocation services are shaped by the machinery, the origin and destination sites, the transport route and how much reinstallation is required. Where a project extends across several production areas, utilities and wider site infrastructure, our whole-plant relocation service covers the broader move.
Dismantling, lifting and movement are planned through our task-based safety approach, including risk assessment, lifting plans, access controls and supervision for each activity.
-
- Industrial machinery relocation
- Heavy machinery relocation
- Machinery moving services
- Industrial equipment moving
- Machinery removal services
- Equipment relocation services
- Single-machine moves
- Production-line relocation
- CNC machine relocation
- Injection moulding machine relocation
- Press relocation
- Packaging machine relocation
- Fragile and sensitive equipment moves
- Internal factory reorganisation
- International machinery relocation
- Phased moves around shutdown windows
- Heavy equipment moving
- Multi-floor and multi-building moves
Industries we support
Need to know more?
Machine Relocation covers individual machines, production cells and complete production lines. Factory & Plant Relocation covers a wider facility move involving several production areas, building services, offices or a whole manufacturing site.
Yes. Our international machine movers have relocated an extrusion line and crystalliser from Italy to Belgium, with local teams supporting individual stages where the route requires it.
Yes, where the site and production plan allow. Moves can be phased around shutdown windows and access restrictions, with machines or production areas removed and reinstalled in stages. Internal moves within a working plant, such as washing-machine drum lines relocated within a plant near Milan, follow the same approach.
Yes, including oversized machines. Lifting and transport methods are chosen from the weight, dimensions, centre of gravity, access route and final position of each machine, and our industrial equipment movers work from a lift plan prepared for that asset.
On a relocation in Italy, Beck & Pollitzer moved 26 production machines to a new manufacturing hall 20 kilometres away. The equipment totalled about 400 tonnes, and the heaviest single machine weighed 85 tonnes. Relocation of production machinery in Italy.
Planning starts with the equipment list, weights and dimensions, drawings or OEM documentation, layouts at both sites, access restrictions, lifting points and the target production schedule. From these we set the dismantling, transport and reinstallation sequence before mobilisation.
Send us the equipment list, both site locations and your target dates, and we will outline how the move could be run.