The Challenge

Moving a production cell between countries without a production gap

Our team in France relocated a complete production cell from France to Morocco for a glass manufacturer, as part of an ongoing relationship with the client. The move had to avoid any disruption to the client’s manufacturing operations, with dismantling, cross-border transport and reinstallation carried out under a strict timeline.


Our Solution

Dismantling, cross-border transport and recommissioning under one programme

Our team in France dismantled the production line at the original site, then coordinated secure cross-border transport of all equipment using four dedicated trucks. Our team in Morocco carried out the reinstallation, recommissioning and the PLC modifications needed to adapt the line to its new site, working alongside the France-based team throughout.

Dismantling of the production line at the original site in France
Secure cross-border transport of all equipment using four dedicated trucks
Full reinstallation and recommissioning of the production cell in Morocco
PLC modifications to adapt the line’s control systems to its new site
Coordination between our local team in Morocco and the France-based team throughout
Dismantling of the production line at the original site in France
Secure cross-border transport of all equipment using four dedicated trucks
Full reinstallation and recommissioning of the production cell in Morocco
PLC modifications to adapt the line’s control systems to its new site
Coordination between our local team in Morocco and the France-based team throughout
Dismantling of the production line at the original site in France
Secure cross-border transport of all equipment using four dedicated trucks
Full reinstallation and recommissioning of the production cell in Morocco
PLC modifications to adapt the line’s control systems to its new site
Coordination between our local team in Morocco and the France-based team throughout
Dismantling of the production line at the original site in France
Secure cross-border transport of all equipment using four dedicated trucks
Full reinstallation and recommissioning of the production cell in Morocco
PLC modifications to adapt the line’s control systems to its new site
Coordination between our local team in Morocco and the France-based team throughout
  • Dismantling of the production line at the original site in France
  • Secure cross-border transport of all equipment using four dedicated trucks
  • Full reinstallation and recommissioning of the production cell in Morocco
  • PLC modifications to adapt the line’s control systems to its new site
  • Coordination between our local team in Morocco and the France-based team throughout

The Outcome

Zero production delays, cross-border move completed to schedule

The production cell was relocated from France to Morocco with zero production delays. Coordination between the France and Morocco teams carried the same programme through dismantling, cross-border transport, reinstallation, PLC modification and recommissioning at the receiving site.

Dedicated trucks
4
Countries
2
Production delays
0

Need to know more?

Why did the relocation involve teams in both France and Morocco?
Dismantling in France and reinstallation in Morocco needed close coordination between both teams so the production cell could be reinstalled and recommissioned at its new location.
Why were PLC modifications needed for the relocated line?
PLC modifications were carried out to adapt the line for the new site in Morocco.
Project Details
  • Client: Glass manufacturer
  • Location: France → Morocco
  • Sector: Building Products
  • Programme: International production cell relocation

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.