Installing six 30-40 tonne oven sections through overhead access, using a 500-tonne mobile crane.

The Challenge
Installing 30-40 tonne oven sections where ground-level access wasn’t possible
Installing heavy oven sections onto pre-installed rails inside a production hall required an alternative access route because tight spatial constraints ruled out conventional ground-level positioning. Our team in the Czech Republic worked alongside a European engineering partner to install a six-section curing oven system, with each section weighing between 30 and 40 tonnes.
Our Solution
A 500-tonne mobile crane accessing the site through the building’s roof
With floor space limited, our engineering team developed an overhead installation strategy, using a 500-tonne mobile crane to access the site through the building’s roof. This required structural engineering assessments of both the building and the crane positioning areas, precision planning for accurate placement onto the pre-installed rail system, and close coordination with rigging specialists throughout.
Structural engineering assessments of the building and crane positioning areas |
Precision planning to ensure accurate positioning onto the pre-installed rail system |
Coordination with rigging specialists throughout the overhead installation |
Safety protocol development for the complex overhead lifting operations |
Compliance with strict European safety standards throughout |
Structural engineering assessments of the building and crane positioning areas |
Precision planning to ensure accurate positioning onto the pre-installed rail system |
Coordination with rigging specialists throughout the overhead installation |
Safety protocol development for the complex overhead lifting operations |
Compliance with strict European safety standards throughout |
-
Structural engineering assessments of the building and crane positioning areas
-
Precision planning to ensure accurate positioning onto the pre-installed rail system
-
Coordination with rigging specialists throughout the overhead installation
-
Safety protocol development for the complex overhead lifting operations
-
Compliance with strict European safety standards throughout
The Outcome
Six oven sections installed on time and within budget
The installation was completed on time and within budget, with all six oven sections positioned on the pre-installed rail system.
Need to know more?
- Client: Building sector manufacturer
- Location: Czech Republic
- Sector: Building Products
- Programme: Curing oven system installation

Plywood and LVL production facility installation in France
- 12 months Programme length
- France Country
- Thébault Group Client

Cross-border production cell relocation for a glass manufacturer
- 4 Dedicated trucks
- 2 Countries
- 0 Production delays

Production line relocation between sister facilities in North Carolina
- 20 pieces Equipment relocated
- 20,000+ lb Heaviest component
- 30 tons Forklift capacity

Production line relocation from Germany to the United Kingdom
- 2 Countries
- match-marking + disconnection + dismantling Origin scope
- press + equipment reinstallation Destination scope

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Automated tyre plant installation in Tangier, Morocco
- 70,560 Planned project hours
- 120 days Duration
- multiple Plant zones

Vulcanisation press relocation from Tunisia to the Czech Republic
- 450 Project hours
- 30 days Duration
- 2 Countries

Aluminium slab casting equipment installation in Belgium
- 40,000+ Project hours
- Lichtervelde, Belgium Location
- Metals & Minerals Sector