Installing automated conveyor and production equipment across multiple plant zones with mechanical and electrical integration.

The Challenge
Integrating automated production equipment across several areas of a new tyre plant
The Tangier programme required mechanical and electrical installation support for automated production lines across multiple plant areas. The scope covered conveyor systems and automated equipment across several production zones as part of the tyre plant development programme.
Our Solution
Mechanical and electrical installation delivered by an integrated site team
Beck & Pollitzer provided site management, mechanical and electrical supervisors and installation crews. Working with the customer’s engineering teams, the team supported internal transport and floor marking before mechanical installation, levelling and alignment of the automated equipment.
• Internal transport and floor marking in coordination with engineering teams
• Mechanical assembly, levelling and alignment
• Cable tray installation and cable routing
• Connection of switch cabinets
The Outcome
Installation support delivered across multiple tyre-production zones
The 120-day programme covered automated conveyor and production equipment across several production zones, with 70,560 planned project hours supporting the mechanical and electrical installation scope.
- Client: Tyre manufacturing project
- Location: Tangier, Morocco
- Sector: Automotive
- Programme: Automated tyre plant installation support
- Timeline: 120 days

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Vulcanisation press relocation from Tunisia to the Czech Republic
- 450 Project hours
- 30 days Duration
- 2 Countries

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

Multi-scope automotive summer shutdown upgrade in Hungary
- 2 weeks Shutdown window
- 20 years of accumulation Legacy cabling removed
- precision levelling and MEWP access Key methods

Nine-robot replacement during an automotive summer shutdown
- 9 Robots replaced
- 20 Team size

Tyre manufacturing plant installation in Tangier, Morocco
- 70,000+ Project hours
- 8+ months Duration
- 5+ km Conveyor systems

24-tonne TEF 220 press installation in the Czech Republic
- 24 tonnes Press weight
- 10 hours Working day
- PT5400 Gantry

Tier 1 automotive factory installation completed in 60 days
- 120 tonnes Machinery installed
- 60 days Timeline
- unloading + positioning + installation Scope
Beck & Pollitzer Industrial Intelligence™