Completing loader rail modifications, overhead conductor installation and removal of 20 years of redundant cabling within a two-week summer shutdown.

The Challenge
Delivering several upgrade scopes inside one fixed summer shutdown window
During a two-week summer shutdown, a Tier 1 automotive manufacturer needed loader rail modifications, a new overhead conductor and removal of redundant cabling completed while several contractors were working on site. The fixed shutdown window meant the work had to be sequenced around other teams without compromising site safety.
Removing cabling that had accumulated over approximately 20 years added a further task that required work at height.
Our Solution
Precision levelling, controlled work-at-height access and segregated work zones
Our Hungarian team combined mechanical upgrade work with structured site coordination. A Leica NA720 was used for high-accuracy levelling, while Haulotte Star10 and HA-15 IP MEWPs provided access for elevated work. Hilti TE 4-22 drills supported the structural modifications required during the shutdown.
On the busy multi-contractor site, non-essential activities were rescheduled, work zones were segregated and clear movement routes were established to reduce overlap between teams. The programme was managed against the two-week shutdown through our project management approach.
Loader rail modifications during the planned shutdown |
Installation of a new overhead conductor |
Removal of approximately 20 years of redundant cabling |
Leica NA720 used for precision levelling |
Haulotte MEWPs used for controlled work at height |
Work zones and movement routes segregated around other contractors |
Loader rail modifications during the planned shutdown |
Installation of a new overhead conductor |
Removal of approximately 20 years of redundant cabling |
Leica NA720 used for precision levelling |
Haulotte MEWPs used for controlled work at height |
Work zones and movement routes segregated around other contractors |
-
Loader rail modifications during the planned shutdown
-
Installation of a new overhead conductor
-
Removal of approximately 20 years of redundant cabling
-
Leica NA720 used for precision levelling
-
Haulotte MEWPs used for controlled work at height
-
Work zones and movement routes segregated around other contractors
The Outcome
Multi-scope upgrade completed within the two-week shutdown
The work was completed during the planned two-week summer shutdown, leaving the client’s production lines ready to restart without delay. Removing the redundant cabling also significantly reduced the load on the roof, which the project manager described as a tangible safety improvement.
Need to know more?
- Client: Tier 1 automotive manufacturer
- Location: Hungary
- Sector: Automotive
- Programme: Multi-scope summer shutdown upgrade
- Timeline: 2 weeks

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Automated tyre plant installation in Tangier, Morocco
- 70,560 Planned project hours
- 120 days Duration
- multiple Plant zones

Vulcanisation press relocation from Tunisia to the Czech Republic
- 450 Project hours
- 30 days Duration
- 2 Countries

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

Nine-robot replacement during an automotive summer shutdown
- 9 Robots replaced
- 20 Team size

Tyre manufacturing plant installation in Tangier, Morocco
- 70,000+ Project hours
- 8+ months Duration
- 5+ km Conveyor systems

24-tonne TEF 220 press installation in the Czech Republic
- 24 tonnes Press weight
- 10 hours Working day
- PT5400 Gantry

Tier 1 automotive factory installation completed in 60 days
- 120 tonnes Machinery installed
- 60 days Timeline
- unloading + positioning + installation Scope