Multi-scope automotive summer shutdown upgrade in Hungary

Completing loader rail modifications, overhead conductor installation and removal of 20 years of redundant cabling within a two-week summer shutdown.

Hungary

The Challenge

Delivering several upgrade scopes inside one fixed summer shutdown window

During a two-week summer shutdown, a Tier 1 automotive manufacturer needed loader rail modifications, a new overhead conductor and removal of redundant cabling completed while several contractors were working on site. The fixed shutdown window meant the work had to be sequenced around other teams without compromising site safety.

Removing cabling that had accumulated over approximately 20 years added a further task that required work at height.


Our Solution

Precision levelling, controlled work-at-height access and segregated work zones

Our Hungarian team combined mechanical upgrade work with structured site coordination. A Leica NA720 was used for high-accuracy levelling, while Haulotte Star10 and HA-15 IP MEWPs provided access for elevated work. Hilti TE 4-22 drills supported the structural modifications required during the shutdown.

On the busy multi-contractor site, non-essential activities were rescheduled, work zones were segregated and clear movement routes were established to reduce overlap between teams. The programme was managed against the two-week shutdown through our project management approach.

Loader rail modifications during the planned shutdown
Installation of a new overhead conductor
Removal of approximately 20 years of redundant cabling
Leica NA720 used for precision levelling
Haulotte MEWPs used for controlled work at height
Work zones and movement routes segregated around other contractors
Loader rail modifications during the planned shutdown
Installation of a new overhead conductor
Removal of approximately 20 years of redundant cabling
Leica NA720 used for precision levelling
Haulotte MEWPs used for controlled work at height
Work zones and movement routes segregated around other contractors
Loader rail modifications during the planned shutdown
Installation of a new overhead conductor
Removal of approximately 20 years of redundant cabling
Leica NA720 used for precision levelling
Haulotte MEWPs used for controlled work at height
Work zones and movement routes segregated around other contractors
Loader rail modifications during the planned shutdown
Installation of a new overhead conductor
Removal of approximately 20 years of redundant cabling
Leica NA720 used for precision levelling
Haulotte MEWPs used for controlled work at height
Work zones and movement routes segregated around other contractors
  • Loader rail modifications during the planned shutdown
  • Installation of a new overhead conductor
  • Removal of approximately 20 years of redundant cabling
  • Leica NA720 used for precision levelling
  • Haulotte MEWPs used for controlled work at height
  • Work zones and movement routes segregated around other contractors

The Outcome

Multi-scope upgrade completed within the two-week shutdown

The work was completed during the planned two-week summer shutdown, leaving the client’s production lines ready to restart without delay. Removing the redundant cabling also significantly reduced the load on the roof, which the project manager described as a tangible safety improvement.

Shutdown window
2 weeks
Legacy cabling removed
20 years of accumulation
Key methods
precision levelling and MEWP access

Need to know more?

Why was removing the old cabling more than a housekeeping task?
Around 20 years of redundant cabling was removed. The project manager described this as a tangible safety improvement, because it significantly reduced the load on the roof as well as clearing obsolete material.
What equipment supported the precision and work-at-height activities?
A Leica NA720 was used for high-accuracy levelling, with Haulotte Star10 and HA-15 IP MEWPs providing aerial access. Hilti TE 4-22 drills were used for structural adjustment work.
Project Details
  • Client: Tier 1 automotive manufacturer
  • Location: Hungary
  • Sector: Automotive
  • Programme: Multi-scope summer shutdown upgrade
  • Timeline: 2 weeks

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.