Decommissioning takes equipment out of service in a controlled order: services are isolated, machinery and supporting systems are dismantled, assets leave site, and the area is prepared for handover, reuse or the next phase of work. Beck & Pollitzer provides industrial decommissioning services for manufacturers retiring equipment, closing production areas or clearing complete facilities.
Manufacturers such as Ford, Novelis and Harsco Metals & Minerals have used our teams for decommissioning and dismantling work. On a separate project, our teams emptied a UK factory to a fixed handover date, processing more than 9,200 tonnes of equipment in 87,000 project hours.
Decommissioning can be booked on its own or as the first stage of a relocation or a new installation. Because the same teams also relocate and install equipment, the dismantling can be planned around what happens to each asset next, whether that is reuse, storage, scrap or a new line.
From isolation to handover
The scope can range from a single redundant machine to a complete plant closure. The areas below follow the work from the first isolation to the final handover.

Isolation, shutdown & preparation
Before machinery is dismantled, the equipment and connected systems are separated from the operating plant. The work is defined around the isolation of electrical, mechanical and piping connections, the removal sequence, access and lifting. Where required, each decommissioning project is set out in a written dismantling plan.
- Electrical and mechanical isolation
- Piping and services disconnection
- Equipment identification and work-area separation
- Written dismantling plan
- Dismantling sequence and access review
- Removal-route preparation

Controlled equipment & plant dismantling
Machinery, production lines, steelwork and connected systems are taken apart in the sequence required for safe removal, including equipment below floor level such as a press and its machine room. Where several work fronts run at the same time, removal sequence and handover milestones holds the removal sequence to the handover date.
- Production-line and plant dismantling
- Mechanical, electrical and piping removal
- Removal of ancillary steelwork and structures
- Machine-room and below-floor removal
- Removal from live production areas
- 24/7 shift planning for tight deadlines

Asset recovery, segregation & disposal
Decommissioned assets follow different routes. Equipment can be kept for reuse, passed to a new site, recycled or scrapped, while steelwork, raw materials and other site contents are processed within the agreed project scope.
- Asset identification and segregation
- Preservation of reusable equipment
- Containerisation of dismantled parts
- Scrap and recyclable-material separation
- Transport to scrap and recycling routes
- Packing and temporary storage where required

Site clearance & handover
The final stage removes remaining equipment and project materials so the agreed area can be handed back to the client or prepared for its next use. Isolation control, lifting activity, access restrictions, simultaneous work fronts and supervision are planned through our clearance-phase safety controls.
- Removal of redundant machinery and equipment
- Clearance of remaining production assets
- Removal of redundant steelwork and materials
- Removal of waste and surplus materials
- Work-area clean-down and release
- Handover against the agreed scope

Technical rigging & retrofit: integrating a Gigafactory with more than 3,500 assets
- 29,467 Project hours
- 117 days Duration
- 3,506 Items relocated

Hydraulic press dismantling completed in nine days
- 9 days Timeline
- 24/7 Shift pattern
- 35 tonnes Heaviest retained component

Four-press line dismantling for international transport
- 4 Presses dismantled
- 2,000 tons Largest press
- 16 weeks Timeline

Dismantling a 5-ton industrial oven using a 7-ton Hyster forklift
- 5 tons Oven weight
- 7 tons Forklift capacity
- Hyster S150 Forklift model

Fridge production line dismantling and relocation programme
- 2 Production lines
- 42 Vehicles deployed
- 10 Listed machines/components

Automotive body shop strip-out completed in 11 weeks
- ~800 tonnes Machinery removed
- 200+ Robots removed
- 11 weeks Timeline

Komatsu forging press dismantling and removal in Hungary
- 2,500 Project hours
- 10 Team
- 500t Power tower

Cardboard press removal under low-clearance and soft-ground conditions
- 91,000 lb New machine weight
- steel plates Ground control
- 3 lifts simultaneously Load management

Packaging line dismantling for new technology in the Czech Republic
- complete dismantling scope Existing line
- mechanical + electrical Disciplines
- operating production facility Environment
Wider decommissioning & dismantling services
The list below shows the wider equipment types and project formats covered alongside the four areas above.
-
- Decommissioning services
- Industrial plant decommissioning
- Production-line decommissioning
- Equipment decommissioning
- Facility decommissioning
- Site decommissioning
- Industrial dismantling services
- Plant dismantling
- Press dismantling and removal
- Robot and cell removal
- Industrial oven dismantling
- Production-equipment strip-out
- Redundant equipment removal
- Factory closure support
- Machinery dismantling
- Equipment reuse preparation
- Material recovery coordination
- CDM Principal Contractor role
Industries we support
Need to know more?
The scope can include isolation and disconnection of electrical, mechanical and piping systems, controlled dismantling, equipment removal, asset segregation, lifting and loading, site clearance and handover. The exact work depends on whether the project covers one machine, a production area or a complete facility. Decommissioning: Process, purpose, key stages & considerations.
Decommissioning takes equipment or a facility out of service. Moving dismantled machinery for reinstallation covers dismantling equipment so it can be transported and reinstalled elsewhere. Some projects combine the two, for example, when part of a line is scrapped, and the rest moves to another site.
Yes. In an 11-week strip-out at a car producer, about 800 tonnes of machinery, including more than 200 robots, were removed from the body shop while the rest of the factory kept producing. Services are isolated, work zones are separated, and removal routes are controlled around the live plant.
Yes, where the project requires it. Beck & Pollitzer can act as Principal Contractor under the CDM regulations, taking responsibility for health and safety management across the dismantling and clearance work.
Yes. Plant closure work can cover production equipment, services, steelwork and raw materials through to clearance and handover, run to a fixed handover date.
Production-equipment strip-out, services removal and associated steelwork can form part of the decommissioning scope. Structural demolition and specialist remediation requirements are assessed separately as part of project scoping.
Retiring one machine or clearing a whole hall starts with the asset list and the handover date. Our team will propose the dismantling sequence.