Dismantling a 5-ton industrial oven using a 7-ton Hyster forklift
Removing a 5-ton oven with a 7-ton Hyster S150 forklift manufactured in 1971 and maintained within Beck & Pollitzer’s equipment fleet.
Decommissioning & Dismantling Ukraine
Ukraine

The Challenge
Removing a 5-ton oven with a long-serving item of lifting equipment
Beck & Pollitzer was asked to dismantle a 5-ton industrial oven. A 7-ton Hyster S150 forklift, manufactured in 1971 and part of the Beck & Pollitzer fleet for decades, was used for the machine dismantling.
Our Solution
7-ton Hyster S150 used to support the oven dismantling
The team used the Hyster S150 to handle the 5-ton oven during dismantling, working under current site safety procedures.
5-ton industrial oven dismantled
7-ton Hyster S150 forklift deployed
Forklift manufactured in 1971 and maintained as part of the equipment fleet
Work carried out under current site safety procedures
5-ton industrial oven dismantled |
7-ton Hyster S150 forklift deployed |
Forklift manufactured in 1971 and maintained as part of the equipment fleet |
Work carried out under current site safety procedures |
5-ton industrial oven dismantled |
7-ton Hyster S150 forklift deployed |
Forklift manufactured in 1971 and maintained as part of the equipment fleet |
Work carried out under current site safety procedures |
5-ton industrial oven dismantled
7-ton Hyster S150 forklift deployed
Forklift manufactured in 1971 and maintained as part of the equipment fleet
Work carried out under current site safety procedures
-
5-ton industrial oven dismantled
-
7-ton Hyster S150 forklift deployed
-
Forklift manufactured in 1971 and maintained as part of the equipment fleet
-
Work carried out under current site safety procedures
The Outcome
5-ton oven dismantling completed
The oven dismantling was completed successfully.
Oven weight
5 tons
Forklift capacity
7 tons
Forklift model
Hyster S150
Forklift year
1971
Project Details
- Location: Ukraine
- Sector: Other Industries
- Programme: Industrial oven dismantling

Decommissioning & Dismantling Czech Republic
Hydraulic press dismantling completed in nine days
- 9 days Timeline
- 24/7 Shift pattern
- 35 tonnes Heaviest retained component

Decommissioning & Dismantling India United Kingdom
Four-press line dismantling for international transport
- 4 Presses dismantled
- 2,000 tons Largest press
- 16 weeks Timeline

Decommissioning & Dismantling Machine Relocation USA
Technical rigging & retrofit: integrating a Gigafactory with more than 3,500 assets
- 29,467 Project hours
- 117 days Duration
- 3,506 Items relocated

Decommissioning & Dismantling Hungary
Fridge production line dismantling and relocation programme
- 2 Production lines
- 42 Vehicles deployed
- 10 Listed machines/components

Decommissioning & Dismantling Hungary
Automotive body shop strip-out completed in 11 weeks
- ~800 tonnes Machinery removed
- 200+ Robots removed
- 11 weeks Timeline

Decommissioning & Dismantling Hungary
Komatsu forging press dismantling and removal in Hungary
- 2,500 Project hours
- 10 Team
- 500t Power tower

Decommissioning & Dismantling USA
Cardboard press removal under low-clearance and soft-ground conditions
- 91,000 lb New machine weight
- steel plates Ground control
- 3 lifts simultaneously Load management

Decommissioning & Dismantling Czech Republic
Packaging line dismantling for new technology in the Czech Republic
- complete dismantling scope Existing line
- mechanical + electrical Disciplines
- operating production facility Environment
Beck & Pollitzer Industrial Intelligence™
Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.

Your next project starts here
Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.