Skip to main content
Vulcanisation press relocation from Tunisia to the Czech Republic

Relocating critical production equipment between two countries without breaking traceability.

Czech Republic
Tunisia

The Challenge

Moving critical production equipment across two countries

International equipment relocations put every stage – dismantling, transport and reinstatement – on a single continuous timeline, since a delay at one end affects the schedule at the other. Beck & Pollitzer supported a Tier 1 automotive components manufacturer with exactly that kind of move, relocating a vulcanisation press from Mateur, Tunisia, to Rudník in the Czech Republic.

With mechanical, electrical and international logistics all needing to align, the project ran across 30 days and 450 project hours, coordinated across two countries rather than a single site.


Our Solution

Match-marked dismantling through to reassembly, one team

Given the equipment’s value and the distance involved, Beck & Pollitzer’s machinery moving team planned each stage to protect the press and maintain component traceability across the move, from initial dismantling through to final positioning in the Czech Republic.

Mechanical and electrical dismantling of the press and associated equipment
Safe electrical isolation, including LOTO procedures and primary power disconnection
Detailed component identification, demarcation and match-marking for traceability
Specialist packing and coordination of overseas transport from Tunisia to the Czech Republic
Positioning, levelling, anchoring and reassembly of the press, conveyors and safety systems at destination
Mechanical and electrical dismantling of the press and associated equipment
Safe electrical isolation, including LOTO procedures and primary power disconnection
Detailed component identification, demarcation and match-marking for traceability
Specialist packing and coordination of overseas transport from Tunisia to the Czech Republic
Positioning, levelling, anchoring and reassembly of the press, conveyors and safety systems at destination
Mechanical and electrical dismantling of the press and associated equipment
Safe electrical isolation, including LOTO procedures and primary power disconnection
Detailed component identification, demarcation and match-marking for traceability
Specialist packing and coordination of overseas transport from Tunisia to the Czech Republic
Positioning, levelling, anchoring and reassembly of the press, conveyors and safety systems at destination
Mechanical and electrical dismantling of the press and associated equipment
Safe electrical isolation, including LOTO procedures and primary power disconnection
Detailed component identification, demarcation and match-marking for traceability
Specialist packing and coordination of overseas transport from Tunisia to the Czech Republic
Positioning, levelling, anchoring and reassembly of the press, conveyors and safety systems at destination
  • Mechanical and electrical dismantling of the press and associated equipment
  • Safe electrical isolation, including LOTO procedures and primary power disconnection
  • Detailed component identification, demarcation and match-marking for traceability
  • Specialist packing and coordination of overseas transport from Tunisia to the Czech Republic
  • Positioning, levelling, anchoring and reassembly of the press, conveyors and safety systems at destination

A 50-tonne mobile crane and high-capacity forklifts supported the lift and placement work at both ends of the move, with match-marking completed during dismantling, streamlining the subsequent machinery installation process in Rudník. For projects where dimensional accuracy is critical, Beck & Pollitzer also draws on industrial metrology and site layout services to support precision alignment and verification.


The Outcome

Reinstated safely across two countries, on schedule

LOTO procedures governing every electrical isolation and reconnection kept the relocation moving safely from dismantling through international transport to full reassembly, without compromising the equipment or the receiving facility’s operational requirements.

The result gave the client a fully reinstalled vulcanisation press, conveyors and associated safety systems in the Czech Republic, completed within the 30-day, 450-hour programme agreed at the outset.

Project hours
450
Duration
30 days
Countries
2
Crane capacity
50 tonnes

Need to know more?

Why was match-marking so important during dismantling?
Detailed component identification and match-marking during dismantling meant every part could be traced and correctly reassembled at the destination, reducing the risk of errors when reinstating the press in the Czech Republic.
Why did the project need LOTO procedures specifically?
Lockout/Tagout (LOTO) procedures governed primary power disconnection and reconnection at both the origin and destination sites, keeping the electrical isolation and reinstatement stages safe throughout.
Project Details
  • Client: Tier 1 automotive components manufacturer
  • Location: Mateur, Tunisia → Rudník, Czech Republic
  • Sector: Automotive
  • Programme: International machinery relocation
  • Timeline: 30 days

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.