Nine-machine installation for a tyre mould manufacturer in Hungary

Moving nine machines through access routes not designed for large equipment
The project required nine machines to be unloaded, transferred through the facility and installed within 18 days. The dimensions of the facility’s doors and gates required careful planning to accommodate the machines, and the internal corridors were unsuited to substantial machinery.
Turnkey handling from unloading through foundations, siting and electrical connection
The team managed unloading and internal transport, then created the required foundations, positioned the machines and completed electrical connections. Machinery was manoeuvred through the restricted access points before being sited in its final position. The project was carried out under Safety, Health and Environment guidelines and included the quality-control requirements set for the installation.
Unloading and internal transfer of nine machines |
Route planning around restricted doors, gates and corridors |
Creation of machine foundations |
Final siting and positioning of equipment |
Electrical connections completed as part of the turnkey scope |
Project delivered under the stated SHE and quality-control requirements |
Unloading and internal transfer of nine machines |
Route planning around restricted doors, gates and corridors |
Creation of machine foundations |
Final siting and positioning of equipment |
Electrical connections completed as part of the turnkey scope |
Project delivered under the stated SHE and quality-control requirements |
-
Unloading and internal transfer of nine machines
-
Route planning around restricted doors, gates and corridors
-
Creation of machine foundations
-
Final siting and positioning of equipment
-
Electrical connections completed as part of the turnkey scope
-
Project delivered under the stated SHE and quality-control requirements
Nine machines installed within the 18-day programme
The turnkey installation was completed successfully within 18 days and met the client’s quality-control expectations.
Need to know more?
- Client: Tyre mould manufacturer
- Location: Hungary
- Sector: Automotive
- Programme: Turnkey machinery installation
- Timeline: 18 days

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Automated tyre plant installation in Tangier, Morocco
- 70,560 Planned project hours
- 120 days Duration
- multiple Plant zones

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

Multi-scope automotive summer shutdown upgrade in Hungary
- 2 weeks Shutdown window
- 20 years of accumulation Legacy cabling removed
- precision levelling and MEWP access Key methods

Nine-robot replacement during an automotive summer shutdown
- 9 Robots replaced
- 20 Team size

Tyre manufacturing plant installation in Tangier, Morocco
- 70,000+ Project hours
- 8+ months Duration
- 5+ km Conveyor systems

24-tonne TEF 220 press installation in the Czech Republic
- 24 tonnes Press weight
- 10 hours Working day
- PT5400 Gantry

Tier 1 automotive factory installation completed in 60 days
- 120 tonnes Machinery installed
- 60 days Timeline
- unloading + positioning + installation Scope