Installing body shop structures, robots and fixtures after unloading nearly 100 containers and 30 trucks at a new EV manufacturing plant in Tamil Nadu.

Turning a large inbound equipment package into a precisely set body shop
The project covered the complete installation of body shop structures and associated equipment at a new EV assembly plant in Tamil Nadu. Before installation could begin, nearly 100 containers and 30 trucks of equipment had to be unloaded, unpacked and checked.
Robots, fixtures and supporting structures then had to be positioned to the required layout before mechanical, electrical and utility interfaces could be completed under OEM and client supervision.
Laser-tracked layout, mechanical and electrical installation, followed by commissioning support
A 50-person team managed the installation sequence from incoming equipment handling through to commissioning support. Laser-tracked floor marking established the installation references before robots, fixtures and supporting structures were positioned, aligned and levelled.
The machinery installation scope also included structural assembly, electrical work and utility connections, supported by cranes, forklifts and scissor lifts. The installation phase ran for 2.5 months, followed by four weeks of commissioning support.
Unloading, unpacking and quality checks for nearly 100 containers and 30 trucks |
Laser-tracked floor marking for layout control |
Positioning and installation of robots, fixtures and supporting structures |
Mechanical and electrical installation, alignment and levelling |
Utility connections and commissioning support |
50-person team supported by cranes, forklifts and scissor lifts |
Unloading, unpacking and quality checks for nearly 100 containers and 30 trucks |
Laser-tracked floor marking for layout control |
Positioning and installation of robots, fixtures and supporting structures |
Mechanical and electrical installation, alignment and levelling |
Utility connections and commissioning support |
50-person team supported by cranes, forklifts and scissor lifts |
-
Unloading, unpacking and quality checks for nearly 100 containers and 30 trucks
-
Laser-tracked floor marking for layout control
-
Positioning and installation of robots, fixtures and supporting structures
-
Mechanical and electrical installation, alignment and levelling
-
Utility connections and commissioning support
-
50-person team supported by cranes, forklifts and scissor lifts
Body shop installation completed on time before four weeks of commissioning support
The installation phase was completed on time over 2.5 months. The team then provided four weeks of commissioning support under OEM and client supervision.
Need to know more?
- Client: Global automotive manufacturer
- Location: Tamil Nadu, India
- Sector: Battery and Electrification; Automotive
- Programme: Body shop installation and commissioning support
- Timeline: 2.5 months installation + 4 weeks commissioning

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

EV manufacturing installation and process utility integration in India
- 10 months Programme duration
- 120 Site team
- 4 Towers erected

Battery cell plant electrical installation in France
- 45,000 Project hours
- 18 months Duration
- electrical integration and installation Scope

Body-in-white installation for an electric vehicle programme
- body sides + final hang-on line + roller tables + lift systems Scope
- compressed design-to-build schedule Constraint

Battery cell production equipment installation at a US Gigafactory
- 8 Electrode lines
- 3 Floors
- 120 operatives Team

Scalable M&E installation: Automated storage & handling for a US battery facility
- 111,328 Project hours
- 15 months Programme length
- 100 Peak workforce

Voltage regulator production facility installation in the USA
- 275 Machines installed
- 250,000 sq ft Facility size
- 8 months Programme duration

Solar glass manufacturing line installation at a renewable energy gigafactory in India
- 6,000+ acres Facility size
- Solar glass, solar PV, battery cells, green hydrogen Production lines on site
Beck & Pollitzer Industrial Intelligence™