Integrating mechanical, electrical and piping systems across four towers over a ten-month programme with a 120-person site team.

Integrating production equipment with electrical, piping and process utilities across four towers
The project required a large-scale industrial installation for an Indian electric vehicle manufacturer, combining machinery handling with mechanical, electrical and piping integration. The scope included process utility connections and work around dosing and mixing systems for anode and cathode processes.
Beyond equipment positioning, the programme also required cable-tray installation, cable laying and termination, piping layout and routing, and integration with plant utilities across a ten-month delivery period.
Mechanical, electrical and piping integration supported by site infrastructure and commissioning checks
A 120-person team managed unloading, unpacking, material handling, positioning and assembly, together with electrical and process-piping work. Four towers were erected as part of the programme, with mechanical, electrical and piping interfaces integrated across the installation.
Electrical work included tray installation, cable laying and termination. The piping scope covered layout design, routing and connections to plant utilities. Local site infrastructure included DG backup, a fabrication yard and dedicated offices for OEM teams.
The team also carried out I/O checks, testing and commissioning support, alongside manpower support for Dry, Wet and PPAP trials. Waste disposal was managed in line with pollution-board requirements, with HSE compliance maintained across the programme.
Unloading, unpacking, material handling, positioning and assembly |
Four towers erected during the ten-month programme |
Electrical tray installation, cable laying and termination |
Piping layout, routing and integration with plant utilities |
Mechanical, electrical and piping integration for anode and cathode dosing/mixing systems |
I/O checks, testing, commissioning support and Dry/Wet/PPAP trial manpower |
Unloading, unpacking, material handling, positioning and assembly |
Four towers erected during the ten-month programme |
Electrical tray installation, cable laying and termination |
Piping layout, routing and integration with plant utilities |
Mechanical, electrical and piping integration for anode and cathode dosing/mixing systems |
I/O checks, testing, commissioning support and Dry/Wet/PPAP trial manpower |
-
Unloading, unpacking, material handling, positioning and assembly
-
Four towers erected during the ten-month programme
-
Electrical tray installation, cable laying and termination
-
Piping layout, routing and integration with plant utilities
-
Mechanical, electrical and piping integration for anode and cathode dosing/mixing systems
-
I/O checks, testing, commissioning support and Dry/Wet/PPAP trial manpower
Ten-month installation programme delivered with additional scope added during the project
The project ran for ten months with a 120-person team, erecting four towers and integrating the mechanical, electrical and piping systems. Key project milestones were met, and additional scope was awarded beyond the initial contract during delivery.
Need to know more?
- Client: Indian electric vehicle manufacturer
- Location: India
- Sector: Battery and Electrification; Automotive
- Programme: Industrial installation and process utility integration
- Timeline: 10 months

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

Battery cell plant electrical installation in France
- 45,000 Project hours
- 18 months Duration
- electrical integration and installation Scope

Body-in-white installation for an electric vehicle programme
- body sides + final hang-on line + roller tables + lift systems Scope
- compressed design-to-build schedule Constraint

Battery cell production equipment installation at a US Gigafactory
- 8 Electrode lines
- 3 Floors
- 120 operatives Team

Scalable M&E installation: Automated storage & handling for a US battery facility
- 111,328 Project hours
- 15 months Programme length
- 100 Peak workforce

Voltage regulator production facility installation in the USA
- 275 Machines installed
- 250,000 sq ft Facility size
- 8 months Programme duration

Solar glass manufacturing line installation at a renewable energy gigafactory in India
- 6,000+ acres Facility size
- Solar glass, solar PV, battery cells, green hydrogen Production lines on site
Beck & Pollitzer Industrial Intelligence™

