Installing body-side assemblies, roller tables, lift systems and associated structures against a compressed design-to-build schedule in California.

Installing body-in-white equipment to a compressed schedule while design changes continued on site
The project required inner and outer body-side equipment, a final hang-on line, roller tables, lift systems and associated structures to be installed for an electric-vehicle programme in California.
The design-to-build period was compressed and multiple modifications had to be carried out with the OEM on site. Wildfires in the California area also disrupted the project supply chain.
Installation teams worked alongside the OEM through modifications and supply constraints
The automotive installation covered the body-in-white assemblies and supporting handling systems, with the team adapting the installation sequence as modifications were made on site.
The project combined machinery installation with direct coordination around the OEM work fronts.
Installation targets maintained during the compressed programme
During this phase of the project, the team was meeting its installation targets despite the compressed programme and wildfire-related supply-chain challenges.
- Client: Electric vehicle manufacturer
- Location: California, USA
- Sector: Battery and Electrification; Automotive
- Programme: Body-in-white production equipment installation
- Timeline: Installation phase ongoing in 2021

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

EV manufacturing installation and process utility integration in India
- 10 months Programme duration
- 120 Site team
- 4 Towers erected

Battery cell plant electrical installation in France
- 45,000 Project hours
- 18 months Duration
- electrical integration and installation Scope

Battery cell production equipment installation at a US Gigafactory
- 8 Electrode lines
- 3 Floors
- 120 operatives Team

Scalable M&E installation: Automated storage & handling for a US battery facility
- 111,328 Project hours
- 15 months Programme length
- 100 Peak workforce

Voltage regulator production facility installation in the USA
- 275 Machines installed
- 250,000 sq ft Facility size
- 8 months Programme duration

Solar glass manufacturing line installation at a renewable energy gigafactory in India
- 6,000+ acres Facility size
- Solar glass, solar PV, battery cells, green hydrogen Production lines on site