Delivering electrical integration, cabling and equipment connections across an 18-month battery manufacturing programme.

Electrical integration across a new battery cell manufacturing plant
A European automotive battery company was establishing a new battery cell plant in France to decarbonise automotive battery production. The client needed a partner to handle the complex electrical integration and installation for the plant’s manufacturing processes.
Electrical calculations, cable installation and busbar-to-cabinet connections
Our team in France provided the plant’s electrical engineering and installation scope. This covered electrical calculations and the integration of all equipment within the plant, the supply and installation of cables and cable trays, and the connections between the busbar and the equipment’s electrical cupboards.
Project management covered the oversight and coordination of the whole programme to meet its deadlines and budget.
Electrical calculations and integration of production equipment |
Supply and installation of cables and cable trays |
Electrical connections between the busbar and equipment electrical cupboards |
Electrical calculations and integration of production equipment |
Supply and installation of cables and cable trays |
Electrical connections between the busbar and equipment electrical cupboards |
-
Electrical calculations and integration of production equipment
-
Supply and installation of cables and cable trays
-
Electrical connections between the busbar and equipment electrical cupboards
45,000 project hours delivered across an 18-month programme
The battery cell plant was completed within 18 months, requiring a total of 45,000 project hours and meeting the client’s standards.
- Client: European automotive battery company
- Location: France
- Sector: Battery and Electrification; Automotive
- Programme: Electrical engineering and installation
- Timeline: 18 months

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

EV manufacturing installation and process utility integration in India
- 10 months Programme duration
- 120 Site team
- 4 Towers erected

Body-in-white installation for an electric vehicle programme
- body sides + final hang-on line + roller tables + lift systems Scope
- compressed design-to-build schedule Constraint

Battery cell production equipment installation at a US Gigafactory
- 8 Electrode lines
- 3 Floors
- 120 operatives Team

Scalable M&E installation: Automated storage & handling for a US battery facility
- 111,328 Project hours
- 15 months Programme length
- 100 Peak workforce

Voltage regulator production facility installation in the USA
- 275 Machines installed
- 250,000 sq ft Facility size
- 8 months Programme duration

Solar glass manufacturing line installation at a renewable energy gigafactory in India
- 6,000+ acres Facility size
- Solar glass, solar PV, battery cells, green hydrogen Production lines on site