Passer au contenu principal
Mechanical installation for a new cold rolling mill and finishing line

Installing over 6,250 tonnes of equipment and 375 km of electrical cabling for a new metals production facility.

India

Installing a new brownfield metals facility at exceptional scale and precision

Our team in India supported a metals manufacturer with the mechanical, electrical and piping installation for a new brownfield Cold Rolling Mill and Finishing Line facility. The scope covered the Cold Rolling Mill, Thick Gauge Slitter, Thin Gauge Slitter, Roll Grinder, Coil Packaging Line, High Speed EOT Cranes and multiple Annealing Furnaces, each demanding highly controlled alignment and safety standards.


Mechanical, electrical and piping installation across the full production line

Working alongside the client and OEM engineers, our team delivered end-to-end industrial installation services covering mechanical works, electrical installation and piping and welding. The mechanical scope included unloading, unpacking, positioning and levelling of all machinery and auxiliaries, with mill baseplate alignment held to within 30 microns and hydraulic torquing of mill housings up to 4,650 kN.

Unloading, unpacking, positioning and levelling of all machinery and auxiliaries, with baseplate alignment to within 30 microns
Hydraulic torquing of mill housings up to 4,650 kN
Cable laying and termination across 375 km, with cable tray fabrication, panel installation, earthing and system loop checks
Fabrication and erection of hydraulic, pneumatic and lubrication piping, with installed pipework pressure-tested for leak integrity
High-capacity lifting using 700-tonne and 250-tonne mobile cranes
Unloading, unpacking, positioning and levelling of all machinery and auxiliaries, with baseplate alignment to within 30 microns
Hydraulic torquing of mill housings up to 4,650 kN
Cable laying and termination across 375 km, with cable tray fabrication, panel installation, earthing and system loop checks
Fabrication and erection of hydraulic, pneumatic and lubrication piping, with installed pipework pressure-tested for leak integrity
High-capacity lifting using 700-tonne and 250-tonne mobile cranes
Unloading, unpacking, positioning and levelling of all machinery and auxiliaries, with baseplate alignment to within 30 microns
Hydraulic torquing of mill housings up to 4,650 kN
Cable laying and termination across 375 km, with cable tray fabrication, panel installation, earthing and system loop checks
Fabrication and erection of hydraulic, pneumatic and lubrication piping, with installed pipework pressure-tested for leak integrity
High-capacity lifting using 700-tonne and 250-tonne mobile cranes
Unloading, unpacking, positioning and levelling of all machinery and auxiliaries, with baseplate alignment to within 30 microns
Hydraulic torquing of mill housings up to 4,650 kN
Cable laying and termination across 375 km, with cable tray fabrication, panel installation, earthing and system loop checks
Fabrication and erection of hydraulic, pneumatic and lubrication piping, with installed pipework pressure-tested for leak integrity
High-capacity lifting using 700-tonne and 250-tonne mobile cranes
  • Unloading, unpacking, positioning and levelling of all machinery and auxiliaries, with baseplate alignment to within 30 microns
  • Hydraulic torquing of mill housings up to 4,650 kN
  • Cable laying and termination across 375 km, with cable tray fabrication, panel installation, earthing and system loop checks
  • Fabrication and erection of hydraulic, pneumatic and lubrication piping, with installed pipework pressure-tested for leak integrity
  • High-capacity lifting using 700-tonne and 250-tonne mobile cranes

Over 6,250 tonnes installed to the tolerances the mill required

The project delivered the complete mechanical installation of more than 6,250 tonnes of equipment and 375 km of electrical cabling, alongside the precision piping scope. Across the Cold Rolling Mill and finishing line, heavy-lift installation was coordinated with baseplate alignment held to within 30 microns.

Equipment installed
6,250+ tonnes
Electrical cabling
375 km
Baseplate alignment tolerance
30 microns
Mobile crane capacity
700 tonnes

Need to know more?

Why did baseplate alignment need to be held to within 30 microns?
The Cold Rolling Mill’s equipment required this level of precision in its baseplate alignment as part of the mechanical installation scope.
Why were 700-tonne and 250-tonne mobile cranes needed for this project?
Installing equipment at this scale, over 6,250 tonnes across the Cold Rolling Mill and Finishing Line, required high-capacity lifting systems capable of handling the heaviest components safely.
Project Details
  • Client: Metals manufacturer
  • Location: India
  • Sector: Metals
  • Programme: Cold rolling mill and finishing line installation

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.