Assembling an extrusion handling system and installing a 4,400-ton press outdoors while plant walls were still under construction.

Installing a 4,400-ton press outdoors while the surrounding plant was still being built
The aluminium project combined assembly of a complete extrusion handling system with installation of a 4,400-ton press. The work ran for several months from winter into summer while sections of the plant remained under construction.
The site team worked through cold, rain and high summer temperatures while heavy installation activities continued outdoors.
Heavy lifting with a 400-ton gantry, R120 forklift and hydraulic press cart
The heavy machinery installation used a 400-ton gantry system, R120 forklift and hydraulic press cart for the extrusion equipment and press.
The project combined heavy-lift planning with ongoing health and safety controls during the outdoor work.
Extrusion handling system and 4,400-ton press completed on time
Both installations were completed on time with safe execution and client satisfaction.
- Client: Aluminium manufacturer
- Location: Southwest USA
- Sector: Metals
- Programme: Extrusion handling system and heavy press installation
- Timeline: Several months from winter through summer

Aluminium slab casting equipment installation in Belgium
- 40,000+ Project hours
- Lichtervelde, Belgium Location
- Metals & Minerals Sector

Greenfield aluminium plant installation in Kathua, Jammu
- 610 days Programme length
- 230 + 25 supervisors Workforce
- 1,400 tonnes Mill capacity

Mechanical installation for a new cold rolling mill and finishing line
- 6,250+ tonnes Equipment installed
- 375 km Electrical cabling
- 30 microns Baseplate alignment tolerance

Main ram housing replacement on a 5,100-ton extrusion press
- 5,100 tons Extrusion press rating
- 400 tons Gantry capacity
- 17 Team size

Three extrusion press and ASRS installation programme in India
- 3 Extrusion presses
- 7, 8 and 10 inch Press sizes
- 150+ Planned team

Production line relocation from Bulgaria to the Netherlands
- 2 Production lines
- furnaces + casting lines + transformers + cooling towers + pumps Main equipment
- cross-Europe Transport

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Automated tyre plant installation in Tangier, Morocco
- 70,560 Planned project hours
- 120 days Duration
- multiple Plant zones