Integrating 28 manual stations, four robotic cells and AGVs beneath 20-foot overhead structures, with no safety incidents.

Integrating robotic cells, manual stations and AGV routes beneath overhead structures
The client needed an industrial equipment installation for a flexible, low-volume assembly line in an engine manufacturing facility, combining 28 manual stations with four robotic cells. One robot weighed more than 15,000 lb, the assembly tools were mounted on 20-foot steel overhead structures, and Automated Guided Vehicles had to move engines between stations along the floor beneath those structures.
Seventeen specialists coordinated mechanical, electrical and utility installation from nine scissor lifts
The 17-person team began in June with offloading and mechanical and electrical installation, including air and lubrication pipelines. The crew worked from nine scissor lifts, with a constant risk of falling tools and materials that made site safety the priority throughout. The assembly stations and robotic cells were coordinated and synchronised, and the AGVs were integrated into the line.
Installation of 28 manual assembly stations |
Installation and integration of four robotic cells |
Handling of a robot weighing more than 15,000 lb |
Assembly tools mounted on 20-foot overhead steel structures |
AGV routes integrated beneath the overhead equipment |
Mechanical and electrical installation plus air and lubrication pipelines |
Nine scissor lifts used during the overhead installation work |
Installation of 28 manual assembly stations |
Installation and integration of four robotic cells |
Handling of a robot weighing more than 15,000 lb |
Assembly tools mounted on 20-foot overhead steel structures |
AGV routes integrated beneath the overhead equipment |
Mechanical and electrical installation plus air and lubrication pipelines |
Nine scissor lifts used during the overhead installation work |
-
Installation of 28 manual assembly stations
-
Installation and integration of four robotic cells
-
Handling of a robot weighing more than 15,000 lb
-
Assembly tools mounted on 20-foot overhead steel structures
-
AGV routes integrated beneath the overhead equipment
-
Mechanical and electrical installation plus air and lubrication pipelines
-
Nine scissor lifts used during the overhead installation work
Integrated assembly system completed with no safety incidents
The project was completed with no safety incidents. Both the OEM and the end user were satisfied with the delivery and planned to collaborate with Beck & Pollitzer on future opportunities.
Need to know more?
- Client: Alternate-fuels technology manufacturer
- Location: North Carolina, USA
- Sector: Other Industries
- Programme: Robotic cell and manual assembly line installation

110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling

1,000-tonne press installation in the Czech Republic
- 1,000 tonnes Press capacity
- 500+ Project hours
- 10 hours Working day

Installation of two vertical presses in the Czech Republic
- 2 Presses installed
- 103 tons and 43 tons Press weights
- 10 hours Working day

Mechanical and electrical installation for a UK plastic recycling plant
- 2 Sorting and wash lines
- 3 Erema extruders
- 1 Water treatment plant

25,000 lb hydraulic brake press installation in South Carolina
- 25,000 lb Press weight
- 15,000 lb Forklift capacity
- VersaLift + rigging booms Main handling equipment

Rigging two 1,600+ ton injection moulding machines in South Carolina
- 2 Machines
- 1,600+ tons each Weight
- 130 tons Crane

Dryer and chimney reinstallation in Ukraine
- 600 tonnes Dryer
- 8m Dryer width
- 85m Chimney height

30-tonne turbine installation and pipe connection in France
- 30 tonnes Heaviest equipment
- positioning + pipe connection + pressure testing + modifications Scope
Beck & Pollitzer Industrial Intelligence™