Three extrusion press and ASRS installation programme in India

Installing 7-, 8- and 10-inch extrusion presses, conveyors, ASRS and finishing systems with electrical and piping utilities across a planned 12-month programme.

India

Integrating extrusion presses, handling, automated storage and finishing equipment in one programme

The aluminium producer‘s installation programme covered three extrusion presses in 7-, 8- and 10-inch sizes, together with handling conveyors, an automated storage and retrieval system, anodising equipment and vertical powder-coating stations.

The scope also included electrical and piping utility installation through to « Power On ».


Machinery, conveyors, ASRS, finishing stations and utilities installed as one scope

Beck & Pollitzer India was assigned the installation of the extrusion presses and associated handling systems, plus the ASRS and finishing equipment. The team was also responsible for electrical and piping utilities up to the « Power On » stage.

The planned programme involved more than 150 skilled people and approximately 380,000 project hours from July 2022 to May 2023.

Installation of 7-, 8- and 10-inch extrusion presses
Conveyor-based handling systems
Automated storage and retrieval system installation
Anodising and vertical powder-coating stations
Electrical and piping utilities through to « Power On »
Planned workforce of more than 150 people
Installation of 7-, 8- and 10-inch extrusion presses
Conveyor-based handling systems
Automated storage and retrieval system installation
Anodising and vertical powder-coating stations
Electrical and piping utilities through to « Power On »
Planned workforce of more than 150 people
Installation of 7-, 8- and 10-inch extrusion presses
Conveyor-based handling systems
Automated storage and retrieval system installation
Anodising and vertical powder-coating stations
Electrical and piping utilities through to « Power On »
Planned workforce of more than 150 people
Installation of 7-, 8- and 10-inch extrusion presses
Conveyor-based handling systems
Automated storage and retrieval system installation
Anodising and vertical powder-coating stations
Electrical and piping utilities through to « Power On »
Planned workforce of more than 150 people
  • Installation of 7-, 8- and 10-inch extrusion presses
  • Conveyor-based handling systems
  • Automated storage and retrieval system installation
  • Anodising and vertical powder-coating stations
  • Electrical and piping utilities through to « Power On »
  • Planned workforce of more than 150 people

Planned 12-month installation programme

The programme was scheduled from July 2022 to May 2023, with more than 150 people and approximately 380,000 project hours planned.

Extrusion presses
3
Press sizes
7, 8 and 10 inch
Planned team
150+
Planned project hours
~380,000
Planned duration
12 months
Project Details
  • Client: Aluminium producer
  • Location: India
  • Sector: Metals
  • Programme: Extrusion press, handling and ASRS installation
  • Timeline: Started July 2022; planned completion May 2023

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.