Internal relocation of three presses in Homberg, Germany

Moving presses weighing up to 44 tonnes between production halls over three weeks, with weekend working, floor adaptations and DGUV V3 testing.

Germany

Moving heavy presses between halls without disrupting core production hours

The manufacturer needed three presses relocated internally at its Homberg plant. Individual equipment packages included the press, control cabinets, reel and drawing machine, with machine weights reaching 44 tonnes.

The work had to take place outside core production hours, and the destination also required floor-pan adaptation and new cable ducts embedded in the floor.


Weekend dismantling and reassembly combined with floor adaptations and formal electrical testing

The internal relocation included mechanical and electrical dismantling, movement between production halls and reassembly at the new locations.

Destination works included adapting the floor pan and installing new cable ducts. Final electrical testing was completed with DGUV V3 documentation, and the relocation activities were scheduled at weekends outside the core production window.

Three presses relocated internally
Equipment packages included presses, control cabinets, reels and drawing machines
Maximum machine weight: 44 tonnes
Mechanical and electrical dismantling and reassembly
Floor-pan adaptation at destination
New cable ducts embedded in the floor
DGUV V3 testing and documentation
Weekend working outside core production hours
Three presses relocated internally
Equipment packages included presses, control cabinets, reels and drawing machines
Maximum machine weight: 44 tonnes
Mechanical and electrical dismantling and reassembly
Floor-pan adaptation at destination
New cable ducts embedded in the floor
DGUV V3 testing and documentation
Weekend working outside core production hours
Three presses relocated internally
Equipment packages included presses, control cabinets, reels and drawing machines
Maximum machine weight: 44 tonnes
Mechanical and electrical dismantling and reassembly
Floor-pan adaptation at destination
New cable ducts embedded in the floor
DGUV V3 testing and documentation
Weekend working outside core production hours
Three presses relocated internally
Equipment packages included presses, control cabinets, reels and drawing machines
Maximum machine weight: 44 tonnes
Mechanical and electrical dismantling and reassembly
Floor-pan adaptation at destination
New cable ducts embedded in the floor
DGUV V3 testing and documentation
Weekend working outside core production hours
  • Three presses relocated internally
  • Equipment packages included presses, control cabinets, reels and drawing machines
  • Maximum machine weight: 44 tonnes
  • Mechanical and electrical dismantling and reassembly
  • Floor-pan adaptation at destination
  • New cable ducts embedded in the floor
  • DGUV V3 testing and documentation
  • Weekend working outside core production hours

Three presses relocated within the three-week programme

The internal relocation was completed on time after three weeks, with final DGUV V3 testing and documentation included in the project scope.

Presses relocated
3
Maximum machine weight
44 tonnes
Timeline
3 weeks
Working window
weekends
Final testing
DGUV V3
Project Details
  • Client: High-strength fasteners manufacturer
  • Location: Homberg, Germany
  • Sector: Other Industries
  • Programme: Internal press relocation
  • Timeline: 3 weeks

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.