Dismantling production lines in Hungary and shipping 450 tons of equipment to Colombia, Sweden and India.

Splitting a Hungarian production facility across three international destinations
A global welding consumables manufacturer was consolidating its European operations and relocating production lines from its Hungarian facility to Colombia, Sweden and India. The programme covered disassembly and packing in Hungary, shipping to three countries and the clearance of the factory once the production lines had been removed.
Disassembly, a 27-container export programme and final site clearance
The team dismantled the mechanical, electrical and piping systems of the production lines and packed the components for transport. Beck & Pollitzer then coordinated the shipping of 27 containers carrying 450 tons of equipment, including customs clearance and coordination with international shipping partners, under a single project management structure.
Once the production lines had been removed, the team handled the dismantling and disposal of the remaining equipment in compliance with environmental regulations, clearing the facility for handover.
Mechanical, electrical and piping disassembly at the Hungarian site |
Packing for international transport |
27 containers shipped to Colombia, Sweden and India |
Customs clearance and coordination with shipping partners |
Dismantling and disposal of remaining equipment for site clearance |
Mechanical, electrical and piping disassembly at the Hungarian site |
Packing for international transport |
27 containers shipped to Colombia, Sweden and India |
Customs clearance and coordination with shipping partners |
Dismantling and disposal of remaining equipment for site clearance |
-
Mechanical, electrical and piping disassembly at the Hungarian site
-
Packing for international transport
-
27 containers shipped to Colombia, Sweden and India
-
Customs clearance and coordination with shipping partners
-
Dismantling and disposal of remaining equipment for site clearance
450 tons of equipment dispatched and the Hungarian site cleared
The project shipped 27 containers containing 450 tons of production equipment to three destination countries. Once the production lines had been removed, the remaining equipment was dismantled and disposed of so the Hungarian facility could be handed over.
Need to know more?
- Client: Global welding consumables manufacturer
- Location: Hungary to Colombia, Sweden and India
- Sector: Other Industries
- Programme: Factory relocation and site clearance

Relocating 15 production machines to a new Czech facility
- 15 Machines relocated
- 75 tonnes Equipment weight
- 330 Project hours

Complete manufacturing plant relocation in Germany
- about 400 truckloads Transport
- up to 250 tonnes Mobile cranes
- 160 tonnes Gantry

First commissioning phase of a German plant relocation
- decommissioning + transport + reassembly + commissioning Scope
- air + process water + power Utilities

Turnkey factory relocation from Coventry to Leamington Spa
- factory relocation + fit-out Scope
- workshops + offices + mezzanines + enclosures Additional works
- on time + on budget Delivery

Principal-contractor delivery for a UK factory relocation
- relocation + M&E + workshops + offices + mezzanines + enclosures Scope
- Principal Contractor Role

Eight-month airlaid plant relocation and reassembly in Germany
- 8 months Duration
- 30+ Trucks
- about 9,000 m² Production area

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling