Moving 12 injection moulding machines and three CNC machines three kilometres between production sites in 330 project hours.

Moving 75 tonnes of production equipment while work ran at both locations
The manufacturer required 12 injection moulding machines and three CNC machines to be transferred from its existing production facility to a new plant three kilometres away. The relocation also included mechanical dismantling, positioning and levelling.
Work was organised for 11 hours per day at both sites simultaneously, creating a tight sequence between dismantling, transport and installation activities.
A ten-person team completed dismantling, transport, positioning and levelling
Beck & Pollitzer Czech acted as the main contractor for the factory relocation, using tackle boxes and a VersaLift 25/35 forklift to handle the equipment.
Fifteen machines and 75 tonnes of equipment relocated in 330 project hours
The relocation was completed successfully. The completed relocation led to a further press-relocation project for the same client in 2023.
- Client: Electrical installation equipment manufacturer
- Location: Czech Republic; 3 km between facilities
- Sector: Other Industries
- Programme: Factory relocation of 12 IMMs and 3 CNC machines
- Timeline: 330 project hours; 11-hour working days

Factory move from Hungary to three international destinations
- 450 tons Equipment shipped
- 27 Containers
- 3 Destination countries

Complete manufacturing plant relocation in Germany
- about 400 truckloads Transport
- up to 250 tonnes Mobile cranes
- 160 tonnes Gantry

First commissioning phase of a German plant relocation
- decommissioning + transport + reassembly + commissioning Scope
- air + process water + power Utilities

Turnkey factory relocation from Coventry to Leamington Spa
- factory relocation + fit-out Scope
- workshops + offices + mezzanines + enclosures Additional works
- on time + on budget Delivery

Principal-contractor delivery for a UK factory relocation
- relocation + M&E + workshops + offices + mezzanines + enclosures Scope
- Principal Contractor Role

Eight-month airlaid plant relocation and reassembly in Germany
- 8 months Duration
- 30+ Trucks
- about 9,000 m² Production area

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling