Turnkey factory relocation from Coventry to Leamington Spa
Completing a full factory move and new-facility fit-out for a power-generation manufacturer, including workshops, offices, mezzanines and enclosures.
Factory/Plant Relocation United Kingdom
United Kingdom

Relocating the factory while fitting out the client’s new production facility
The manufacturer required its existing factory to move from Coventry to a new facility in Leamington Spa. The project combined machinery relocation with additional fit-out work inside the new building.
Principal relocation contractor for the move and supporting facility works
The turnkey factory relocation covered the total installation project, including the equipment move and installation of internal workshops, offices, mezzanine floors and enclosures.
Factory relocation and fit-out delivered on time and on budget
The project was completed on time and on budget, followed by a formal handover with the client.
Scope
factory relocation + fit-out
Additional works
workshops + offices + mezzanines + enclosures
Delivery
on time + on budget
Project Details
- Client: Power-generation equipment manufacturer
- Location: Coventry to Leamington Spa, UK
- Sector: Other Industries
- Programme: Turnkey factory relocation and facility fit-out
- Timeline: Completed on time and on budget

Factory/Plant Relocation Hungary India Sweden
Factory move from Hungary to three international destinations
- 450 tons Equipment shipped
- 27 Containers
- 3 Destination countries

Factory/Plant Relocation République tchèque
Relocating 15 production machines to a new Czech facility
- 15 Machines relocated
- 75 tonnes Equipment weight
- 330 Project hours

Factory/Plant Relocation Germany
Complete manufacturing plant relocation in Germany
- about 400 truckloads Transport
- up to 250 tonnes Mobile cranes
- 160 tonnes Gantry

Factory/Plant Relocation Germany
First commissioning phase of a German plant relocation
- decommissioning + transport + reassembly + commissioning Scope
- air + process water + power Utilities

Factory/Plant Relocation United Kingdom
Principal-contractor delivery for a UK factory relocation
- relocation + M&E + workshops + offices + mezzanines + enclosures Scope
- Principal Contractor Role

Factory/Plant Relocation Germany
Eight-month airlaid plant relocation and reassembly in Germany
- 8 months Duration
- 30+ Trucks
- about 9,000 m² Production area

Factory/Plant Relocation Machinery Installation Site Planning & Health & Safety Saudi Arabia
HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Machinery Installation République tchèque
110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling
Beck & Pollitzer Industrial Intelligence™
Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.

Your next project starts here
Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.