Dismantling and moving a complete airlaid process on more than 30 trucks before reassembling a 75-metre line in a 9,000 m² production area.

Moving a complete process line and rebuilding it to tight dimensional requirements
The existing airlaid plant had to be dismantled, lifted and transported to a new German site. More than 30 trucks, including special transports, were used to move the plant components.
At the destination, a 25-person mechanical and electrical team had to rebuild a process approximately 75 metres long and seven metres high within a production area of about 9,000 m².
Dismantling, crane loading, special transport and precision reassembly
The factory relocation began with dismantling the old plant before components were crane-loaded for transport to the new site.
Airlaid system handed over ready for start-up in February 2021
The eight-month relocation concluded with handover of the reassembled system in February 2021. The client praised the handling, flexibility and completion to schedule.
- Client: Germany-based manufacturing client
- Location: Germany
- Sector: Other Industries
- Programme: Airlaid plant relocation and reassembly
- Timeline: 8 months; handed over February 2021

Factory move from Hungary to three international destinations
- 450 tons Equipment shipped
- 27 Containers
- 3 Destination countries

Relocating 15 production machines to a new Czech facility
- 15 Machines relocated
- 75 tonnes Equipment weight
- 330 Project hours

Complete manufacturing plant relocation in Germany
- about 400 truckloads Transport
- up to 250 tonnes Mobile cranes
- 160 tonnes Gantry

First commissioning phase of a German plant relocation
- decommissioning + transport + reassembly + commissioning Scope
- air + process water + power Utilities

Turnkey factory relocation from Coventry to Leamington Spa
- factory relocation + fit-out Scope
- workshops + offices + mezzanines + enclosures Additional works
- on time + on budget Delivery

Principal-contractor delivery for a UK factory relocation
- relocation + M&E + workshops + offices + mezzanines + enclosures Scope
- Principal Contractor Role

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling