Decommissioning, transporting and recommissioning 5-axis machining centres as the first phase of a wider Hannover-to-Laatzen plant relocation.

Restarting the first relocated machining centres while the wider plant move continued
The first phase required existing machinery to be decommissioned, disconnected and prepared for transport from Hannover to Laatzen. Geometry had to be measured before disassembly so the machines could be reassembled and commissioned at the new site.
Decommissioning, transport, reassembly and utility installation under one project team
Project management coordinated the first-phase relocation, while the assembly team handled mechanical and electrical disconnections, packing, transport and reassembly.
First 5-axis machining centres commissioned at the new Laatzen site
The first commissioning operations were completed successfully, establishing the first operational phase of the wider plant relocation programme.
- Client: Industrial machinery manufacturer
- Location: Hannover to Laatzen, Germany
- Sector: Other Industries
- Programme: Plant relocation and first commissioning phase
- Timeline: First phase completed before full relocation

Factory move from Hungary to three international destinations
- 450 tons Equipment shipped
- 27 Containers
- 3 Destination countries

Relocating 15 production machines to a new Czech facility
- 15 Machines relocated
- 75 tonnes Equipment weight
- 330 Project hours

Complete manufacturing plant relocation in Germany
- about 400 truckloads Transport
- up to 250 tonnes Mobile cranes
- 160 tonnes Gantry

Turnkey factory relocation from Coventry to Leamington Spa
- factory relocation + fit-out Scope
- workshops + offices + mezzanines + enclosures Additional works
- on time + on budget Delivery

Principal-contractor delivery for a UK factory relocation
- relocation + M&E + workshops + offices + mezzanines + enclosures Scope
- Principal Contractor Role

Eight-month airlaid plant relocation and reassembly in Germany
- 8 months Duration
- 30+ Trucks
- about 9,000 m² Production area

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling