Fuel injection pump production line move: Germany to Czech Republic

Moving two fuel injection pump production lines from Munich to České Budějovice using 30 trucks over 11 weeks.

République tchèque
Germany

Match-marking two production lines for accurate reassembly

Two fuel injection pump production lines had to be moved from a facility in Munich, Germany, to a production site in České Budějovice, Czech Republic. The main challenge was the precise match-marking of both mechanical and electrical components, which was crucial for the reassembly and functionality of the lines at their new location.


Dismantling, packaging and a 30-truck transport programme

The scope covered the complete dismantling, packaging and transportation of both production lines, followed by their reinstallation at the new location. Thirty trucks were used for the transport, each loaded and offloaded using 3-ton forklifts.

The 11-week programme ran from July to September 2023, supported by detailed planning and coordination across the team.

Mechanical and electrical match-marking before dismantling
Complete dismantling and packaging of both production lines
Thirty-truck transport programme between Germany and the Czech Republic
Reinstallation at the new production site
Mechanical and electrical match-marking before dismantling
Complete dismantling and packaging of both production lines
Thirty-truck transport programme between Germany and the Czech Republic
Reinstallation at the new production site
Mechanical and electrical match-marking before dismantling
Complete dismantling and packaging of both production lines
Thirty-truck transport programme between Germany and the Czech Republic
Reinstallation at the new production site
Mechanical and electrical match-marking before dismantling
Complete dismantling and packaging of both production lines
Thirty-truck transport programme between Germany and the Czech Republic
Reinstallation at the new production site
  • Mechanical and electrical match-marking before dismantling
  • Complete dismantling and packaging of both production lines
  • Thirty-truck transport programme between Germany and the Czech Republic
  • Reinstallation at the new production site

Two production lines relocated safely and on time

The relocation was completed safely, on time and in full compliance with quality standards over 11 weeks, with match-marking supporting accurate reassembly at the receiving site.

Production lines
2
Trucks
30
Forklifts
3-ton
Timeline
11 weeks

Need to know more?

Why was match-marking needed on both mechanical and electrical components?
The two lines were being dismantled and reinstalled at a different facility, so precise identification of mechanical and electrical components was crucial for their reassembly and functionality.
Project Details
  • Location: Munich, Germany to České Budějovice, Czech Republic
  • Sector: Automotive
  • Programme: International production line move
  • Timeline: 11 weeks (July to September 2023)

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.