Dismantling, relocating and reinstalling 31 machines across four halls despite delays in hall readiness.

Relocating 31 machines across four halls despite delayed hall readiness
The programme covered dismantling and relocating 31 machines across four industrial halls totalling more than 2,000 m², while keeping disruption to the existing infrastructure to a minimum. Unforeseen obstacles, including delayed hall readiness, added complexity to the automotive relocation programme.
Relocation combined with new infrastructure, electrical, piping and lining works
Across 3,237 project hours, the team dismantled and relocated the 31 machines and reinstalled them. New infrastructure was constructed in an unused area of the site, meeting safety standards for machine installation, and the team handled the electrical, piping and lining requirements for the relocated machines.
Dismantling, relocation and reinstallation of 31 machines |
Four industrial halls covering more than 2,000 m² |
3,237 project hours delivered |
New infrastructure constructed in an unused site area |
Electrical, piping and lining requirements completed for relocated equipment |
Work completed despite delayed hall readiness |
Dismantling, relocation and reinstallation of 31 machines |
Four industrial halls covering more than 2,000 m² |
3,237 project hours delivered |
New infrastructure constructed in an unused site area |
Electrical, piping and lining requirements completed for relocated equipment |
Work completed despite delayed hall readiness |
-
Dismantling, relocation and reinstallation of 31 machines
-
Four industrial halls covering more than 2,000 m²
-
3,237 project hours delivered
-
New infrastructure constructed in an unused site area
-
Electrical, piping and lining requirements completed for relocated equipment
-
Work completed despite delayed hall readiness
All 31 machines relocated and installed before the estimated deadline
All 31 machines were relocated and installed before the estimated deadline, to the client’s complete satisfaction.
Need to know more?
- Client: Automotive OEM partner
- Location: Hungary
- Sector: Automotive
- Programme: Multi-hall machinery relocation and installation

Cylinder head and block production line relocation: Poland to Brazil
- 50,000 Working hours
- 337 Trucks dispatched
- 2 Production lines relocated

Fuel injection pump production line move: Germany to Czech Republic
- 2 Production lines
- 30 Trucks
- 3-ton Forklifts

Automated stamping machine relocation for an automotive technology supplier
- project manager, assembly supervisor and around 10 skilled workers Core team
- relocation through to commissioning Scope
- weekly with the client Planning

Five-week relocation of a 180-tonne extrusion line in Australia
- 180 tonnes Line weight
- 130 tonnes Main press
- 27 x 40 ft Containers

Staged automotive machinery relocation from Germany to Hungary
- 3,000 Project hours
- 10 Relocation stages
- mechanical + electrical + transport Scope

Mild-hybrid underbody line installation for an automotive manufacturer
- 2,100 Project hours
- 13 operatives Team
- no reported incidents or accidents Safety outcome

Heavy machinery relocation from Poland to India in three shipping batches
- ~80 tonnes Total equipment weight
- ~8-10 tonnes Individual machines
- 3 Shipping batches

Machinery relocation from Hungary to Slovakia
- 5 weeks Timeline
- 2 Countries
- COVID restrictions + strict schedule Constraints