Relocation of 31 machines across four automotive halls in Hungary

Dismantling, relocating and reinstalling 31 machines across four halls despite delays in hall readiness.

Hungary

Relocating 31 machines across four halls despite delayed hall readiness

The programme covered dismantling and relocating 31 machines across four industrial halls totalling more than 2,000 m², while keeping disruption to the existing infrastructure to a minimum. Unforeseen obstacles, including delayed hall readiness, added complexity to the automotive relocation programme.


Relocation combined with new infrastructure, electrical, piping and lining works

Across 3,237 project hours, the team dismantled and relocated the 31 machines and reinstalled them. New infrastructure was constructed in an unused area of the site, meeting safety standards for machine installation, and the team handled the electrical, piping and lining requirements for the relocated machines.

Dismantling, relocation and reinstallation of 31 machines
Four industrial halls covering more than 2,000 m²
3,237 project hours delivered
New infrastructure constructed in an unused site area
Electrical, piping and lining requirements completed for relocated equipment
Work completed despite delayed hall readiness
Dismantling, relocation and reinstallation of 31 machines
Four industrial halls covering more than 2,000 m²
3,237 project hours delivered
New infrastructure constructed in an unused site area
Electrical, piping and lining requirements completed for relocated equipment
Work completed despite delayed hall readiness
Dismantling, relocation and reinstallation of 31 machines
Four industrial halls covering more than 2,000 m²
3,237 project hours delivered
New infrastructure constructed in an unused site area
Electrical, piping and lining requirements completed for relocated equipment
Work completed despite delayed hall readiness
Dismantling, relocation and reinstallation of 31 machines
Four industrial halls covering more than 2,000 m²
3,237 project hours delivered
New infrastructure constructed in an unused site area
Electrical, piping and lining requirements completed for relocated equipment
Work completed despite delayed hall readiness
  • Dismantling, relocation and reinstallation of 31 machines
  • Four industrial halls covering more than 2,000 m²
  • 3,237 project hours delivered
  • New infrastructure constructed in an unused site area
  • Electrical, piping and lining requirements completed for relocated equipment
  • Work completed despite delayed hall readiness

All 31 machines relocated and installed before the estimated deadline

All 31 machines were relocated and installed before the estimated deadline, to the client’s complete satisfaction.

Machines relocated
31
Industrial halls
4
Area
2,000+ m²
Project hours
3,237

Need to know more?

What infrastructure work was included?
New infrastructure was constructed in an unused area of the site, meeting safety standards for machine installation, along with the electrical, piping and lining work for the relocated machines.
Project Details
  • Client: Automotive OEM partner
  • Location: Hungary
  • Sector: Automotive
  • Programme: Multi-hall machinery relocation and installation

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.