Pre-assembling a 20-tonne NMP recovery unit on a 20 m x 8 m mezzanine before moving the 45-tonne assembled system into position with a 400-tonne gantry.

Positioning a fully assembled NMP recovery system beneath restricted headroom
The battery industrialisation centre required an NMP recovery unit to be positioned in an area with restricted headroom. The unit itself weighed 20,000 kg, while the fully assembled system reached 45,000 kg.
The access condition meant the installation method had to account for both the weight of the assembled equipment and the limited vertical space at the destination.
Pre-assembly on a bespoke mezzanine followed by a 400-tonne gantry move
Working with the client and a specialist engineering team, Beck & Pollitzer pre-assembled the NMP recovery unit on a bespoke 20 m x 8 m mezzanine platform.
A 400-tonne lifting gantry was then used to move the fully assembled 45,000 kg system into its final position under the restricted headroom.
20,000 kg NMP recovery unit pre-assembled before final positioning |
Bespoke 20 m x 8 m mezzanine used for pre-assembly |
Fully assembled system weight: 45,000 kg |
400-tonne gantry used for final movement into position |
Delivery coordinated with the client and specialist engineering team |
20,000 kg NMP recovery unit pre-assembled before final positioning |
Bespoke 20 m x 8 m mezzanine used for pre-assembly |
Fully assembled system weight: 45,000 kg |
400-tonne gantry used for final movement into position |
Delivery coordinated with the client and specialist engineering team |
-
20,000 kg NMP recovery unit pre-assembled before final positioning
-
Bespoke 20 m x 8 m mezzanine used for pre-assembly
-
Fully assembled system weight: 45,000 kg
-
400-tonne gantry used for final movement into position
-
Delivery coordinated with the client and specialist engineering team
NMP recovery unit assembled and positioned at the battery industrialisation centre
The installation was completed safely, with the fully assembled NMP recovery system moved into position using the 400-tonne gantry.
- Client: Battery industrialisation centre
- Location: Midlands, United Kingdom
- Sector: Battery and Electrification
- Programme: NMP recovery unit installation

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Scalable M&E installation: Automated storage & handling for a US battery facility
- 111,328 Project hours
- 15 months Programme length
- 100 Peak workforce

Voltage regulator production facility installation in the USA
- 275 Machines installed
- 250,000 sq ft Facility size
- 8 months Programme duration

Solar glass manufacturing line installation at a renewable energy gigafactory in India
- 6,000+ acres Facility size
- Solar glass, solar PV, battery cells, green hydrogen Production lines on site

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

EV manufacturing installation and process utility integration in India
- 10 months Programme duration
- 120 Site team
- 4 Towers erected

Battery cell plant electrical installation in France
- 45,000 Project hours
- 18 months Duration
- electrical integration and installation Scope

Body-in-white installation for an electric vehicle programme
- body sides + final hang-on line + roller tables + lift systems Scope
- compressed design-to-build schedule Constraint
Beck & Pollitzer Industrial Intelligence™