45-tonne NMP recovery unit installation under restricted headroom

Pre-assembling a 20-tonne NMP recovery unit on a 20 m x 8 m mezzanine before moving the 45-tonne assembled system into position with a 400-tonne gantry.

United Kingdom

Positioning a fully assembled NMP recovery system beneath restricted headroom

The battery industrialisation centre required an NMP recovery unit to be positioned in an area with restricted headroom. The unit itself weighed 20,000 kg, while the fully assembled system reached 45,000 kg.

The access condition meant the installation method had to account for both the weight of the assembled equipment and the limited vertical space at the destination.


Pre-assembly on a bespoke mezzanine followed by a 400-tonne gantry move

Working with the client and a specialist engineering team, Beck & Pollitzer pre-assembled the NMP recovery unit on a bespoke 20 m x 8 m mezzanine platform.

A 400-tonne lifting gantry was then used to move the fully assembled 45,000 kg system into its final position under the restricted headroom.

20,000 kg NMP recovery unit pre-assembled before final positioning
Bespoke 20 m x 8 m mezzanine used for pre-assembly
Fully assembled system weight: 45,000 kg
400-tonne gantry used for final movement into position
Delivery coordinated with the client and specialist engineering team
20,000 kg NMP recovery unit pre-assembled before final positioning
Bespoke 20 m x 8 m mezzanine used for pre-assembly
Fully assembled system weight: 45,000 kg
400-tonne gantry used for final movement into position
Delivery coordinated with the client and specialist engineering team
20,000 kg NMP recovery unit pre-assembled before final positioning
Bespoke 20 m x 8 m mezzanine used for pre-assembly
Fully assembled system weight: 45,000 kg
400-tonne gantry used for final movement into position
Delivery coordinated with the client and specialist engineering team
20,000 kg NMP recovery unit pre-assembled before final positioning
Bespoke 20 m x 8 m mezzanine used for pre-assembly
Fully assembled system weight: 45,000 kg
400-tonne gantry used for final movement into position
Delivery coordinated with the client and specialist engineering team
  • 20,000 kg NMP recovery unit pre-assembled before final positioning
  • Bespoke 20 m x 8 m mezzanine used for pre-assembly
  • Fully assembled system weight: 45,000 kg
  • 400-tonne gantry used for final movement into position
  • Delivery coordinated with the client and specialist engineering team

NMP recovery unit assembled and positioned at the battery industrialisation centre

The installation was completed safely, with the fully assembled NMP recovery system moved into position using the 400-tonne gantry.

NMP unit
20,000 kg
Fully assembled lift
45,000 kg
Mezzanine
20 m x 8 m
Gantry capacity
400 tonnes
Project Details
  • Client: Battery industrialisation centre
  • Location: Midlands, United Kingdom
  • Sector: Battery and Electrification
  • Programme: NMP recovery unit installation

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.