Relocating a large laminating machine through a constrained-access route in Ukraine, using an alternative handling method where crane access wasn’t feasible.

Relocating machinery within a space-constrained packaging facility
Beck & Pollitzer is carrying out the relocation of a Nordmeccanica Duplex Combi Linear L1300 laminating machine at the client’s packaging facility in Sumy, Ukraine. The machine plays a key role in the client’s packaging production process, and space constraints at the site limited the handling methods available for dismantling and transport.
Two forklifts in tandem, led by our Chief Engineer
Given the site’s space constraints, crane handling was not feasible for the safe removal of a 6-tonne furnace. Instead, our team used two forklifts in tandem for that specific task, while the wider dismantling and transport of the laminating machine was led on-site by our Chief Engineer as part of the relocation.
Precise dismantling and transportation of the laminating machine as part of the ongoing relocation |
Use of two forklifts in tandem to remove a 6-tonne furnace where space constraints made crane handling unfeasible |
On-site work led by our Chief Engineer throughout the relocation |
Precise dismantling and transportation of the laminating machine as part of the ongoing relocation |
Use of two forklifts in tandem to remove a 6-tonne furnace where space constraints made crane handling unfeasible |
On-site work led by our Chief Engineer throughout the relocation |
-
Precise dismantling and transportation of the laminating machine as part of the ongoing relocation
-
Use of two forklifts in tandem to remove a 6-tonne furnace where space constraints made crane handling unfeasible
-
On-site work led by our Chief Engineer throughout the relocation
Relocation underway using an alternative handling method
The relocation is being executed at the Sumy facility, where constrained access has required alternative handling methods. Two forklifts were used in tandem for the safe removal of a 6-tonne furnace where crane handling was not feasible, while the dismantling and transport of the Nordmeccanica laminating machine is being led on site by our Chief Engineer.
Need to know more?
- Client: Packaging manufacturer
- Location: Sumy, Ukraine
- Sector: Paper, Canning & Packaging
- Programme: Laminating machine relocation

Cosmetic bottling line relocation: Ohio to Texas
- 42 Components relocated
- 13,000+ lbs Heaviest component
- 4 weeks Timeline

132,000 lb stamping press installation in South Carolina
- 132,000 lb Press weight
- 400 tons Gantry capacity
- 4 Team

Mechanical and electrical canning line installation in a live plant
- 79 Operatives
- ~60 tons Power and control cable
- ~15 tons Cable routes

Spray packaging production line installation in the Czech Republic
- 1,580 Project hours
- 40 cm Roof clearance
- VersaLift 40/60, Hyster 7-tonne FLT and MEWP Handling equipment

Cardboard press removal under low-clearance and soft-ground conditions
- 91,000 lb New machine weight
- steel plates Ground control
- 3 lifts simultaneously Load management

Aluminium can production equipment installation in Chelyabinsk
- production equipment + steel structures + conveyors Scope
- compressed air, water, drain and vacuum Utilities

Packaging line dismantling for new technology in the Czech Republic
- complete dismantling scope Existing line
- mechanical + electrical Disciplines
- operating production facility Environment

Technical rigging & retrofit: integrating a Gigafactory with more than 3,500 assets
- 29,467 Project hours
- 117 days Duration
- 3,506 Items relocated