Installing a new canning line beside active production, with approximately 60 tons of cable and 15 tons of cable routes.

Installing beside active production without contaminating or disrupting adjacent lines
Our Hungarian team was contracted to complete the mechanical and electrical installation of a new canning line for a beverage client within a live production environment. Working next to an active production area meant the installation had to avoid any contamination of existing production lines, while conveyors and electrical cabinets were installed onto steel-structure platforms without disrupting operations.
Seventy-nine operatives coordinated machinery installation and extensive electrical works
The team completed the mechanical and electrical installation of the canning-line equipment, beginning with offloading, internal movement and precise alignment. The scope continued through assembly and connection of the line, installation and cabling of main power distribution boards, and work on conveyors and electrical cabinets mounted to the steel structures. Across the programme, 79 operatives installed approximately 60 tons of power and control cable and around 15 tons of cable routes.
Careful coordination with the client, focused logistics and heightened safety measures protected both personnel and production integrity.
Offloading, internal movement and precise alignment of canning-line machinery |
Mechanical assembly and connection of line components |
Installation and cabling of main electrical power distribution boards |
Installation of conveyors and electrical cabinets to steel-structure platforms |
Approximately 60 tons of power and control cable installed |
Approximately 15 tons of cable routes installed |
Work coordinated around adjacent live production |
Offloading, internal movement and precise alignment of canning-line machinery |
Mechanical assembly and connection of line components |
Installation and cabling of main electrical power distribution boards |
Installation of conveyors and electrical cabinets to steel-structure platforms |
Approximately 60 tons of power and control cable installed |
Approximately 15 tons of cable routes installed |
Work coordinated around adjacent live production |
-
Offloading, internal movement and precise alignment of canning-line machinery
-
Mechanical assembly and connection of line components
-
Installation and cabling of main electrical power distribution boards
-
Installation of conveyors and electrical cabinets to steel-structure platforms
-
Approximately 60 tons of power and control cable installed
-
Approximately 15 tons of cable routes installed
-
Work coordinated around adjacent live production
Canning-line installation completed after eight months of live-site work
The installation was completed successfully after eight months, with the mechanical equipment, conveyors, distribution boards, cable routes and cabling installed within the live production environment.
Need to know more?
- Client: Beverage manufacturer
- Location: Hungary
- Sector: Consumer Goods; Paper, Canning & Packaging
- Programme: Mechanical and electrical canning line installation
- Timeline: 8 months

Cosmetic bottling line relocation: Ohio to Texas
- 42 Components relocated
- 13,000+ lbs Heaviest component
- 4 weeks Timeline

132,000 lb stamping press installation in South Carolina
- 132,000 lb Press weight
- 400 tons Gantry capacity
- 4 Team

Spray packaging production line installation in the Czech Republic
- 1,580 Project hours
- 40 cm Roof clearance
- VersaLift 40/60, Hyster 7-tonne FLT and MEWP Handling equipment

Aluminium can production equipment installation in Chelyabinsk
- production equipment + steel structures + conveyors Scope
- compressed air, water, drain and vacuum Utilities

Laminating machine relocation in a space-constrained facility in Ukraine
- Nordmeccanica Duplex Combi Linear L1300 Equipment
- Ongoing Project status

Cardboard press removal under low-clearance and soft-ground conditions
- 91,000 lb New machine weight
- steel plates Ground control
- 3 lifts simultaneously Load management

Packaging line dismantling for new technology in the Czech Republic
- complete dismantling scope Existing line
- mechanical + electrical Disciplines
- operating production facility Environment

Turnkey hygiene production line installation in France
- 4,500 Project hours
- 2 months Duration
- 232 Containers unloaded
Beck & Pollitzer Industrial Intelligence™
