Cosmetic bottling line relocation: Ohio to Texas

Relocating a cosmetic bottling line’s 42 components, including a 13,000+ lb packaging unit.

USA

Relocating 42 components, including a 13,000+ lb unit, within four weeks

Our team in the USA relocated a cosmetic bottling line from Ohio to Texas for a cosmetics manufacturer. The move covered 42 major and delicate components, the largest of them a packaging unit weighing over 13,000 lbs.


Mechanical and electrical disassembly through to complete reassembly of 42 components

Our team managed the bottling line relocation from end to end: mechanical and electrical disassembly, packing and loading in Ohio, then unloading and complete reassembly of 42 major and delicate components at the new Texas facility. The largest component, a packaging unit weighing over 13,000 lbs, was moved into the new production line as part of the same programme.

Mechanical and electrical disassembly of the bottling line in Ohio
Packing, loading and transport of 42 major and delicate components
Unloading and complete reassembly at the new Texas facility
Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line
Mechanical and electrical disassembly of the bottling line in Ohio
Packing, loading and transport of 42 major and delicate components
Unloading and complete reassembly at the new Texas facility
Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line
Mechanical and electrical disassembly of the bottling line in Ohio
Packing, loading and transport of 42 major and delicate components
Unloading and complete reassembly at the new Texas facility
Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line
Mechanical and electrical disassembly of the bottling line in Ohio
Packing, loading and transport of 42 major and delicate components
Unloading and complete reassembly at the new Texas facility
Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line
  • Mechanical and electrical disassembly of the bottling line in Ohio
  • Packing, loading and transport of 42 major and delicate components
  • Unloading and complete reassembly at the new Texas facility
  • Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line

42 components reassembled within a four-week programme

The bottling line was fully relocated from Ohio to Texas within four weeks, with all 42 components, including the 13,000+ lb packaging unit, reassembled at the destination facility.

Components relocated
42
Heaviest component
13,000+ lbs
Timeline
4 weeks
Project Details
  • Client: Cosmetics manufacturer
  • Location: Ohio → Texas, USA
  • Sector: Paper, Canning & Packaging; Consumer Goods
  • Programme: Cosmetic bottling line relocation
  • Timeline: 4 weeks

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.