Relocating a cosmetic bottling line’s 42 components, including a 13,000+ lb packaging unit.

Relocating 42 components, including a 13,000+ lb unit, within four weeks
Our team in the USA relocated a cosmetic bottling line from Ohio to Texas for a cosmetics manufacturer. The move covered 42 major and delicate components, the largest of them a packaging unit weighing over 13,000 lbs.
Mechanical and electrical disassembly through to complete reassembly of 42 components
Our team managed the bottling line relocation from end to end: mechanical and electrical disassembly, packing and loading in Ohio, then unloading and complete reassembly of 42 major and delicate components at the new Texas facility. The largest component, a packaging unit weighing over 13,000 lbs, was moved into the new production line as part of the same programme.
Mechanical and electrical disassembly of the bottling line in Ohio |
Packing, loading and transport of 42 major and delicate components |
Unloading and complete reassembly at the new Texas facility |
Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line |
Mechanical and electrical disassembly of the bottling line in Ohio |
Packing, loading and transport of 42 major and delicate components |
Unloading and complete reassembly at the new Texas facility |
Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line |
-
Mechanical and electrical disassembly of the bottling line in Ohio
-
Packing, loading and transport of 42 major and delicate components
-
Unloading and complete reassembly at the new Texas facility
-
Relocation of the largest component, a 13,000+ lb packaging unit, into the new production line
42 components reassembled within a four-week programme
The bottling line was fully relocated from Ohio to Texas within four weeks, with all 42 components, including the 13,000+ lb packaging unit, reassembled at the destination facility.
- Client: Cosmetics manufacturer
- Location: Ohio → Texas, USA
- Sector: Paper, Canning & Packaging; Consumer Goods
- Programme: Cosmetic bottling line relocation
- Timeline: 4 weeks

Mechanical and electrical canning line installation in a live plant
- 79 Operatives
- ~60 tons Power and control cable
- ~15 tons Cable routes

Laminating machine relocation in a space-constrained facility in Ukraine
- Nordmeccanica Duplex Combi Linear L1300 Equipment
- Ongoing Project status

132,000 lb stamping press installation in South Carolina
- 132,000 lb Press weight
- 400 tons Gantry capacity
- 4 Team

Spray packaging production line installation in the Czech Republic
- 1,580 Project hours
- 40 cm Roof clearance
- VersaLift 40/60, Hyster 7-tonne FLT and MEWP Handling equipment

Cardboard press removal under low-clearance and soft-ground conditions
- 91,000 lb New machine weight
- steel plates Ground control
- 3 lifts simultaneously Load management

Aluminium can production equipment installation in Chelyabinsk
- production equipment + steel structures + conveyors Scope
- compressed air, water, drain and vacuum Utilities

Packaging line dismantling for new technology in the Czech Republic
- complete dismantling scope Existing line
- mechanical + electrical Disciplines
- operating production facility Environment

Refrigerator production line relocation: Hungary to Egypt
- 250+ Machines assembled
- 2 Countries
- 3 Teams collaborating