Moving a Meca DACH-300 press through a modified building opening before raising it into position with a 400-ton gantry.

Getting a 132,000 lb press through the building and into final position
Our team in the USA installed a Meca DACH-300 stamping press for a steel and aluminium food-can and tray provider. The press weighed 132,000 lb and measured 240 in x 187 in x 112 in. It was first offloaded outside and moved onto a platform built next to the building, then skated inside through an opening created by removing a section of the building’s side.
Heavy rigging through a modified access route, then 400-ton gantry installation
Inside the building, an 80k rigger lift and two knuckle booms were used to move the press through the facility. The route included several turns, so the heavy-haul dollies had to be reset a number of times. A 400-ton gantry system then rigged the press upright and secured it in its designated position, and four isolating pads were bolted to its base.
The machinery installation scope also covered the decoiler and the rail to the upright platform for material handling. Four riggers and technicians completed the eight-day programme, which was mechanical only, with no electrical or piping work, and followed strict safety protocols throughout.
Offloading outside and transfer onto a purpose-built platform |
Removal of a section of the building’s side to skate the press inside |
Internal movement using an 80k rigger lift, two knuckle booms and heavy-haul dollies |
Upright rigging and positioning with a 400-ton gantry |
Four isolating pads bolted to the press base |
Decoiler and material-handling rail installation |
Offloading outside and transfer onto a purpose-built platform |
Removal of a section of the building’s side to skate the press inside |
Internal movement using an 80k rigger lift, two knuckle booms and heavy-haul dollies |
Upright rigging and positioning with a 400-ton gantry |
Four isolating pads bolted to the press base |
Decoiler and material-handling rail installation |
-
Offloading outside and transfer onto a purpose-built platform
-
Removal of a section of the building’s side to skate the press inside
-
Internal movement using an 80k rigger lift, two knuckle booms and heavy-haul dollies
-
Upright rigging and positioning with a 400-ton gantry
-
Four isolating pads bolted to the press base
-
Decoiler and material-handling rail installation
Press installed in eight days with no reported safety incidents
The stamping press was moved through the facility, raised upright and secured in its designated position, with the decoiler and material-handling rail also installed. No health or safety incidents were reported during the eight-day programme.
Need to know more?
- Client: Steel and aluminium food-can and tray provider
- Location: Lancaster, South Carolina, USA
- Sector: Paper, Canning & Packaging
- Programme: Heavy stamping press installation
- Timeline: 8 days

Mechanical and electrical canning line installation in a live plant
- 79 Operatives
- ~60 tons Power and control cable
- ~15 tons Cable routes

Spray packaging production line installation in the Czech Republic
- 1,580 Project hours
- 40 cm Roof clearance
- VersaLift 40/60, Hyster 7-tonne FLT and MEWP Handling equipment

Aluminium can production equipment installation in Chelyabinsk
- production equipment + steel structures + conveyors Scope
- compressed air, water, drain and vacuum Utilities

Laminating machine relocation in a space-constrained facility in Ukraine
- Nordmeccanica Duplex Combi Linear L1300 Equipment
- Ongoing Project status

Cosmetic bottling line relocation: Ohio to Texas
- 42 Components relocated
- 13,000+ lbs Heaviest component
- 4 weeks Timeline

Cardboard press removal under low-clearance and soft-ground conditions
- 91,000 lb New machine weight
- steel plates Ground control
- 3 lifts simultaneously Load management

Packaging line dismantling for new technology in the Czech Republic
- complete dismantling scope Existing line
- mechanical + electrical Disciplines
- operating production facility Environment

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed