Relocating machinery and utilities from Hannover to Laatzen over six months, including around 400 truckloads and cranes up to 250 tonnes.

Relocating equipment from multiple departments while preserving machine geometry and control data
The relocation covered machinery, systems and equipment from manufacturing, technical, R&D, training, warehouse and assembly areas. Before dismantling the machining centres, control data had to be secured and each machine’s condition and geometry documented.
The programme also required utilities and lifting resources to move with the installation sequence, including compressed air, process water and electrical supplies.
General-contractor delivery from dismantling through utilities and recommissioning
The factory relocation covered mechanical and electrical disassembly, packing, loading, transport, reassembly and recommissioning. Machine geometry was restored from the pre-move records before functions were put back into operation.
Hannover-to-Laatzen relocation completed on schedule with no reported incidents
The six-month relocation was completed on schedule. The project was delivered without incident under the site health and safety requirements.
- Client: Industrial machinery manufacturer
- Location: Hannover to Laatzen, Germany
- Sector: Other Industries
- Programme: Complete plant relocation and recommissioning
- Timeline: Around 6 months

Factory move from Hungary to three international destinations
- 450 tons Equipment shipped
- 27 Containers
- 3 Destination countries

Relocating 15 production machines to a new Czech facility
- 15 Machines relocated
- 75 tonnes Equipment weight
- 330 Project hours

First commissioning phase of a German plant relocation
- decommissioning + transport + reassembly + commissioning Scope
- air + process water + power Utilities

Turnkey factory relocation from Coventry to Leamington Spa
- factory relocation + fit-out Scope
- workshops + offices + mezzanines + enclosures Additional works
- on time + on budget Delivery

Principal-contractor delivery for a UK factory relocation
- relocation + M&E + workshops + offices + mezzanines + enclosures Scope
- Principal Contractor Role

Eight-month airlaid plant relocation and reassembly in Germany
- 8 months Duration
- 30+ Trucks
- about 9,000 m² Production area

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling