Installing service mezzanines, 1,444 grid cells and 36 robots after an incomplete site forced a two-month demobilisation.

The Challenge
Restarting an Autostore installation after the site was suspended on day one
The Greensboro project covered a goods-to-person Autostore system with complete mechanical and electrical installation. The planned start was suspended on the same day because the site was incomplete.
Beck & Pollitzer then loaded, transported and stored the project equipment and materials until work could restart. The project remained demobilised for two months before resuming in mid-August.
Our Solution
Equipment storage and remobilisation followed by mezzanine, grid and robot installation
After the suspension, the team managed the equipment and materials off site until remobilisation. Once work resumed, the installation scope included service and overhang mezzanines, 1,444 grid cells and 36 robots.
The installation scope was mechanical and electrical, with the work executed safely following the delayed launch.
Project equipment and materials loaded, transported and stored after site suspension |
Two-month demobilisation before work restarted |
Service and overhang mezzanine assembly |
1,444 Autostore grid cells |
36 robots |
Mechanical and electrical installation |
Project equipment and materials loaded, transported and stored after site suspension |
Two-month demobilisation before work restarted |
Service and overhang mezzanine assembly |
1,444 Autostore grid cells |
36 robots |
Mechanical and electrical installation |
-
Project equipment and materials loaded, transported and stored after site suspension
-
Two-month demobilisation before work restarted
-
Service and overhang mezzanine assembly
-
1,444 Autostore grid cells
-
36 robots
-
Mechanical and electrical installation
The Outcome
Installation restarted after a two-month demobilisation
Work restarted in mid-August after a two-month demobilisation, with completion planned for early October.
- Client: Clothing distribution centre operator
- Location: Greensboro, North Carolina, USA
- Sector: Warehouse Automation; Consumer Goods
- Programme: Autostore mechanical and electrical installation
- Timeline: Two-month demobilisation; restarted mid-August with completion planned for early October

Automated cold-store warehouse installation for a dairy producer
- 3 sets Steel structures installed
- 45 specialists + 3 engineering/safety staff Installation team
- <50 mm Crane-to-ceiling clearance

AS/RS installation with 19 aisle cranes in Ohio
- 19 Aisle cranes
- cranes + pallet conveyors Main systems
- zero reported incidents/accidents Safety outcome

AutoStore installation for an online food retailer in Texas
- AutoStore + conveyor infrastructure Systems
- conveyor delivery delay Constraint
- AutoStore work reprioritised Programme response

Bespoke customer fulfilment centre installation in Japan
- Chiba City, Japan Location
- First CFC of its kind in Asia Pacific Region

Warehouse automation installations across four tyre-manufacturing sites
- 200,000+ Project hours
- 4 Client locations
- 2 Countries

Automated warehouse capacity expansion in Germany
- 80 Sorting stations installed
- 350+ Autonomous robots inducted
- 30 Vehicles unloaded

Electrical controls installation for an automated warehouse in Warrington
- 20 PLC cabinets
- 88 miles Control cable
- 6,500 m conveyor + 1,800 m shuttle Containment

High-security automated document storage system installation
- 24,000+ Grid cells
- 140 Robots
- 3 Chambers