Spray packaging production line installation in the Czech Republic

Unloading, positioning and levelling a spray packaging production line within a roof clearance of only 40 cm.

Czech Republic

The Challenge

Positioning production equipment beneath a roof structure with only 40 cm clearance

The packaging manufacturer required a spray packaging production line to be unloaded, moved to its installation area, positioned and levelled. The main physical constraint was the space below the roof structure, where only 40 cm of free clearance was available.


Our Solution

VersaLift, 7-tonne forklift and MEWP used for handling and positioning

The team managed the installation sequence from destination unloading and unpacking through to positioning, levelling and handover. A VersaLift 40/60, Hyster 7-tonne forklift and MEWP supported movement and access within the restricted area.

Health and safety planning formed part of the installation before the equipment was moved into position.

Destination unloading and unpacking from wooden boxes
Internal movement to the installation location
Machine manoeuvring, installation, positioning and levelling
VersaLift 40/60, Hyster 7-tonne forklift and MEWP used during the work
Health and safety planning and final handover
Destination unloading and unpacking from wooden boxes
Internal movement to the installation location
Machine manoeuvring, installation, positioning and levelling
VersaLift 40/60, Hyster 7-tonne forklift and MEWP used during the work
Health and safety planning and final handover
Destination unloading and unpacking from wooden boxes
Internal movement to the installation location
Machine manoeuvring, installation, positioning and levelling
VersaLift 40/60, Hyster 7-tonne forklift and MEWP used during the work
Health and safety planning and final handover
Destination unloading and unpacking from wooden boxes
Internal movement to the installation location
Machine manoeuvring, installation, positioning and levelling
VersaLift 40/60, Hyster 7-tonne forklift and MEWP used during the work
Health and safety planning and final handover
  • Destination unloading and unpacking from wooden boxes
  • Internal movement to the installation location
  • Machine manoeuvring, installation, positioning and levelling
  • VersaLift 40/60, Hyster 7-tonne forklift and MEWP used during the work
  • Health and safety planning and final handover

The Outcome

Production line installation completed on schedule across 1,580 project hours

The installation was completed on schedule after 1,580 project hours. The equipment was positioned and levelled within the restricted roof-clearance condition.

Project hours
1,580
Roof clearance
40 cm
Handling equipment
VersaLift 40/60, Hyster 7-tonne FLT and MEWP
Project Details
  • Client: Packaging manufacturer
  • Location: Czech Republic
  • Sector: Paper, Canning & Packaging
  • Programme: Spray packaging production line installation
  • Timeline: Completed end of 2022

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.