Planning the phased relocation of nine multi-axial machining centres and pallet storage units into a new production hall while manufacturing continued.

The Challenge
Relocating a machining production sector while the wider manufacturing operation continued
The heavy-duty drive components manufacturer planned to move a mechanical-processing production sector into a new production hall while ongoing production continued. The initial equipment package included nine multi-axial machining centres with pallet storage units from Mandelli, SSB and Hüller-Hille.
Our Solution
Machine-by-machine identification, dismantling, transport and reinstallation through to operational readiness
The relocation programme was planned across several weeks and included measuring and labelling, electrical and mechanical disassembly, packing and loading, destination unloading and integration, and mechanical and electrical installation.
The scope also included commissioning of a Hüller-Hille machining centre and its pallet storage system, with project sequencing planned around ongoing production.
Nine multi-axial machining centres with pallet storage units |
Measuring and equipment labelling |
Mechanical and electrical disassembly |
Packaging and loading for movement |
Destination unloading and integration |
Mechanical and electrical installation to operational readiness |
Commissioning scope for a Hüller-Hille machining centre and pallet storage |
Nine multi-axial machining centres with pallet storage units |
Measuring and equipment labelling |
Mechanical and electrical disassembly |
Packaging and loading for movement |
Destination unloading and integration |
Mechanical and electrical installation to operational readiness |
Commissioning scope for a Hüller-Hille machining centre and pallet storage |
-
Nine multi-axial machining centres with pallet storage units
-
Measuring and equipment labelling
-
Mechanical and electrical disassembly
-
Packaging and loading for movement
-
Destination unloading and integration
-
Mechanical and electrical installation to operational readiness
-
Commissioning scope for a Hüller-Hille machining centre and pallet storage
The Outcome
Relocation planned over several weeks around ongoing production
The planned sequence covered the relocation through to operational readiness, including commissioning of the specified Hüller-Hille equipment.
- Client: Heavy-duty drive components manufacturer
- Location: Germany
- Sector: Automotive
- Programme: Machining-sector relocation
- Timeline: Several weeks planned

Vulcanisation press relocation from Tunisia to the Czech Republic
- 450 Project hours
- 30 days Duration
- 2 Countries

Cylinder head and block production line relocation: Poland to Brazil
- 50,000 Working hours
- 337 Trucks dispatched
- 2 Production lines relocated

Fuel injection pump production line move: Germany to Czech Republic
- 2 Production lines
- 30 Trucks
- 3-ton Forklifts

Automated stamping machine relocation for an automotive technology supplier
- project manager, assembly supervisor and around 10 skilled workers Core team
- relocation through to commissioning Scope
- weekly with the client Planning

Five-week relocation of a 180-tonne extrusion line in Australia
- 180 tonnes Line weight
- 130 tonnes Main press
- 27 x 40 ft Containers

Relocation of 31 machines across four automotive halls in Hungary
- 31 Machines relocated
- 4 Industrial halls
- 2,000+ m² Area

Staged automotive machinery relocation from Germany to Hungary
- 3,000 Project hours
- 10 Relocation stages
- mechanical + electrical + transport Scope

Mild-hybrid underbody line installation for an automotive manufacturer
- 2,100 Project hours
- 13 operatives Team
- no reported incidents or accidents Safety outcome