Disassembling and moving four cutting machines through a two-phase programme while coordinating temporary storage, reassembly and final delivery with no end-customer downtime.

The Challenge
Sequencing four machine moves around storage, temporary reassembly and other equipment flows
The food-packaging group needed four cutting machines moved from France to Italy without interrupting the end customer. The work was split into two phases and had to be coordinated with the receiving and dispatching of other machinery so transport capacity could be used efficiently.
Our Solution
Three machines moved in phase one before the final Tiger cutting machine followed in phase two
Phase one covered the disassembly of the Leopard, Baghera and RB4 cutting machines. Depending on the equipment route, machines were transported to logistics centres for storage or temporary reassembly before onward movement.
Phase two covered the Tiger cutting machine, including disassembly, transport and reassembly at the destination. Project sequencing aligned the dismantling and reassembly activities with other incoming and outgoing machinery movements.
Phase-one disassembly of Leopard, Baghera and RB4 cutting machines |
Transport to logistics centres for storage or temporary reassembly |
Phase-two disassembly and movement of the Tiger cutting machine |
Reassembly at the destination |
Coordination with other machinery receiving and dispatching activities |
Phase-one disassembly of Leopard, Baghera and RB4 cutting machines |
Transport to logistics centres for storage or temporary reassembly |
Phase-two disassembly and movement of the Tiger cutting machine |
Reassembly at the destination |
Coordination with other machinery receiving and dispatching activities |
-
Phase-one disassembly of Leopard, Baghera and RB4 cutting machines
-
Transport to logistics centres for storage or temporary reassembly
-
Phase-two disassembly and movement of the Tiger cutting machine
-
Reassembly at the destination
-
Coordination with other machinery receiving and dispatching activities
The Outcome
Four cutting machines moved with no downtime to the end customer
The complete machinery transportation programme was delivered in two phases with no downtime to the end customer.
- Client: Food-packaging group
- Location: France to Italy
- Sector: Other Industries
- Programme: Two-phase machinery transportation

International tooling logistics across five European countries
- up to 50 Supplier locations
- 500+ Trucks used
- 5 Collection countries

110-tonne and 40-tonne press installation in Žacléř
- 2 Presses installed
- 110 tonnes + 40 tonnes Press weights
- gantry + VersaLift 40/60 + 5-tonne FLT + 10-m cherry picker Handling

Production line relocation in Italy
- 2,900 Project hours
- 21 days Duration
- 12 On-site team

Hydraulic press dismantling completed in nine days
- 9 days Timeline
- 24/7 Shift pattern
- 35 tonnes Heaviest retained component

Turnkey machinery relocation for an electrical components manufacturer
- 3,000 Project hours
- 5 operatives Core team
- match-marking through to reassembly Scope

Four-press line dismantling for international transport
- 4 Presses dismantled
- 2,000 tons Largest press
- 16 weeks Timeline

Extrusion line and crystalliser move: Italy to Belgium
- 17 days Timeline
- 5 Trucks
- extrusion line, crystalliser and dosing units Equipment

1,000-tonne press installation in the Czech Republic
- 1,000 tonnes Press capacity
- 500+ Project hours
- 10 hours Working day