Delivering scalable automated storage capacity across a high-density construction programme at a US battery facility.

The Challenge
Scaling capacity within a high-density construction programme
As battery and EV manufacturers scale up to meet growing demand for electrified powertrains, expanding automated storage and material handling capacity within a high-density construction programme has become a defining capacity challenge. Beck & Pollitzer delivered automated storage and material handling installation at a major US battery manufacturing facility in Kansas, working with a global advanced manufacturing and construction management partner.
During delivery, project scope grew by 76%, and up to 50 contractors worked concurrently on site. This meant maintaining installation quality and safety on a live construction site, while the programme itself kept expanding, over a schedule extending to 15 months, without disrupting the wider build.
Our Solution
Rigging, ASRS installation and electrical integration by one team
Because scope and site conditions kept changing, Beck & Pollitzer mobilised a single team to carry the installation from unloading and rigging through to electrical integration and commissioning, rather than handing scope between separate contractors at each stage.
Unloaded and rigged equipment across seven operational areas |
Installed two ASRS systems and 17 storage and retrieval machines |
Delivered more than 1,500 feet of STV conveyance infrastructure |
Integrated cable tray, panel and control wiring with the facility’s warehouse management system |
Managed resourcing through a 76% scope increase without a break in progress |
Unloaded and rigged equipment across seven operational areas |
Installed two ASRS systems and 17 storage and retrieval machines |
Delivered more than 1,500 feet of STV conveyance infrastructure |
Integrated cable tray, panel and control wiring with the facility’s warehouse management system |
Managed resourcing through a 76% scope increase without a break in progress |
-
Unloaded and rigged equipment across seven operational areas
-
Installed two ASRS systems and 17 storage and retrieval machines
-
Delivered more than 1,500 feet of STV conveyance infrastructure
-
Integrated cable tray, panel and control wiring with the facility’s warehouse management system
-
Managed resourcing through a 76% scope increase without a break in progress
The Outcome
Scalable warehouse automation, zero safety incidents
A single, continuously adjusted plan, rather than a fixed one, let Beck & Pollitzer complete the programme safely despite the 76% scope increase and the density of the site, logging zero recordable safety incidents across more than 111,000 project hours.
The completed systems give the facility automated material handling capacity that scales with production, supporting the wider shift toward electrified powertrains without adding disruption as output grows.
Need to know more?
- Client: Advanced manufacturing & construction management partner (for a battery facility)
- Location: Kansas, US
- Sector: Automotive (Battery & EV)
- Programme: M&E installation
- Timeline: 15 months

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Voltage regulator production facility installation in the USA
- 275 Machines installed
- 250,000 sq ft Facility size
- 8 months Programme duration

Solar glass manufacturing line installation at a renewable energy gigafactory in India
- 6,000+ acres Facility size
- Solar glass, solar PV, battery cells, green hydrogen Production lines on site

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

EV manufacturing installation and process utility integration in India
- 10 months Programme duration
- 120 Site team
- 4 Towers erected

Battery cell plant electrical installation in France
- 45,000 Project hours
- 18 months Duration
- electrical integration and installation Scope

Body-in-white installation for an electric vehicle programme
- body sides + final hang-on line + roller tables + lift systems Scope
- compressed design-to-build schedule Constraint

45-tonne NMP recovery unit installation under restricted headroom
- 20,000 kg NMP unit
- 45,000 kg Fully assembled lift
- 20 m x 8 m Mezzanine