Installing and commissioning a coffee roasting plant’s complex system components over a year-long programme.

The Challenge
Installing complex roasting systems within a year-long programme
Our team in Germany is carrying out the installation and assembly of a coffee roasting plant in Järfälla, Sweden, for a leading European supplier of coffee processing machines and systems. With 20 specialists on site over a year-long programme, the scope combines dust filtration, roasting machinery, exhaust air purification, conveyor and packaging systems, and the project’s logistical and technical challenges require precise planning and execution.
Our Solution
Dust filtration, roasting machinery and exhaust purification systems, sequenced across a year
The project includes the complete installation of dust filter and green coffee systems, piping and positioning of filter systems, and construction of steel platforms and roof ducts, alongside installation of the roasting machines themselves, exhaust air purification systems, and conveyor and packaging systems.
Installation of dust filter and green coffee systems, including piping and positioning of filter systems |
Construction of steel platforms and roof ducts |
Installation of roasting machines and technical steel structures |
Assembly and piping of PROFORTE exhaust air purification systems |
Installation of conveyor pipes and weighing units |
Installation of dust filter and green coffee systems, including piping and positioning of filter systems |
Construction of steel platforms and roof ducts |
Installation of roasting machines and technical steel structures |
Assembly and piping of PROFORTE exhaust air purification systems |
Installation of conveyor pipes and weighing units |
-
Installation of dust filter and green coffee systems, including piping and positioning of filter systems
-
Construction of steel platforms and roof ducts
-
Installation of roasting machines and technical steel structures
-
Assembly and piping of PROFORTE exhaust air purification systems
-
Installation of conveyor pipes and weighing units
The Outcome
Installation progressing across a year-long programme
Planned milestones have been met on time so far, with installation and commissioning continuing across the year-long programme. The ongoing scope covers dust filtration, roasting machinery, exhaust air purification, conveyor systems and weighing units, supported by a 20-specialist on-site team.
Need to know more?
- Client: Coffee processing equipment supplier
- Location: Järfälla, Sweden
- Sector: Consumer Goods
- Programme: Coffee roasting plant installation and assembly
- Timeline: 1 year

Turnkey hygiene production line installation in France
- 4,500 Project hours
- 2 months Duration
- 232 Containers unloaded

Complex production tank rigging & installation in Poland
- 40 Project hours
- 1 day Duration
- 4 Team size

Mechanical and electrical canning line installation in a live plant
- 79 Operatives
- ~60 tons Power and control cable
- ~15 tons Cable routes

Installation of three 28-metre agricultural grain silos in Hungary
- 3 Silos installed
- 28 m Installation height
- 80,000+ Screws used

Autostore installation for a clothing distribution centre in North Carolina
- 1,444 Grid cells
- 36 Robots
- service + overhang mezzanines Systems

Automated cold-store warehouse installation for a dairy producer
- 3 sets Steel structures installed
- 45 specialists + 3 engineering/safety staff Installation team
- <50 mm Crane-to-ceiling clearance

AS/RS installation with 19 aisle cranes in Ohio
- 19 Aisle cranes
- cranes + pallet conveyors Main systems
- zero reported incidents/accidents Safety outcome

AutoStore installation for an online food retailer in Texas
- AutoStore + conveyor infrastructure Systems
- conveyor delivery delay Constraint
- AutoStore work reprioritised Programme response