Installing 120 tonnes of machinery and equipment at a new Hungarian manufacturing facility, including precision placement of a melting furnace and multi-OEM coordination.

Tier 1 automotive factory installation completed in 60 days

Hungary

The Challenge

Installing 120 tonnes of machinery from multiple OEMs inside a fixed 60-day programme

The Tier 1 automotive supplier required machinery and equipment installed at a new European headquarters and manufacturing facility. The 120-tonne equipment package included a melting furnace that required precise positioning, with several OEM interfaces to coordinate during the installation.


Our Solution

Heavy handling, precision furnace positioning and multi-OEM coordination under one installation programme

The team managed loading and unloading, internal movement, positioning and machinery installation using forklifts, cherry pickers and high-capacity cranes.

Project sequencing coordinated the installation programme and the interfaces between the client, OEM teams and site activities through the 60-day programme.

Loading and unloading of machinery and equipment
Internal movement and positioning
Precision placement of the melting furnace
Mechanical installation of the equipment package
Forklifts, cherry pickers and high-capacity cranes used
Multiple OEM interfaces coordinated through the programme
Loading and unloading of machinery and equipment
Internal movement and positioning
Precision placement of the melting furnace
Mechanical installation of the equipment package
Forklifts, cherry pickers and high-capacity cranes used
Multiple OEM interfaces coordinated through the programme
Loading and unloading of machinery and equipment
Internal movement and positioning
Precision placement of the melting furnace
Mechanical installation of the equipment package
Forklifts, cherry pickers and high-capacity cranes used
Multiple OEM interfaces coordinated through the programme
Loading and unloading of machinery and equipment
Internal movement and positioning
Precision placement of the melting furnace
Mechanical installation of the equipment package
Forklifts, cherry pickers and high-capacity cranes used
Multiple OEM interfaces coordinated through the programme
  • Loading and unloading of machinery and equipment
  • Internal movement and positioning
  • Precision placement of the melting furnace
  • Mechanical installation of the equipment package
  • Forklifts, cherry pickers and high-capacity cranes used
  • Multiple OEM interfaces coordinated through the programme

The Outcome

120 tonnes of machinery installed within the 60-day programme

The installation was completed within the stated 60-day timeframe, and no project issues were reported during delivery.

Machinery installed
120 tonnes
Timeline
60 days
Scope
unloading + positioning + installation
Coordination
multiple OEMs
Project Details
  • Client: Tier 1 automotive parts supplier
  • Location: Hungary
  • Sector: Automotive
  • Programme: Factory machinery installation
  • Timeline: 60 days

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.