Replacing the main ram housing and accessory cylinders on a 5,100-ton aluminium extrusion press in Texas within a three-week deadline.

The Challenge
Replacing a major press assembly within a three-week production window
The aluminium manufacturer needed the main ram housing and accessory cylinders replaced on a 5,100-ton extrusion press in Texas within a three-week deadline. The existing housing had to be removed and replaced with a new pre-assembled unit, while an inclined ramp and the weight of the housing created additional handling challenges.
Our Solution
Seventeen-person team and 400-ton gantry used for dismantling and replacement
A 17-person team of riggers, millwrights and engineers carried out the machinery replacement, dismantling the existing ram housing and accessory cylinders and installing the new pre-assembled housing and cylinder package. A 400-ton gantry handled the heavy lifting, and dedicated Health & Safety staff developed safety strategies for the inclined ramp and the weight of the housing.
Dismantling of the existing main ram housing and accessory cylinders |
Installation of a new pre-assembled main ram housing and cylinder package |
400-ton gantry used for controlled heavy lifting |
Seventeen riggers, millwrights and engineers deployed |
Safety strategies developed for the inclined ramp and heavy housing |
Dismantling of the existing main ram housing and accessory cylinders |
Installation of a new pre-assembled main ram housing and cylinder package |
400-ton gantry used for controlled heavy lifting |
Seventeen riggers, millwrights and engineers deployed |
Safety strategies developed for the inclined ramp and heavy housing |
-
Dismantling of the existing main ram housing and accessory cylinders
-
Installation of a new pre-assembled main ram housing and cylinder package
-
400-ton gantry used for controlled heavy lifting
-
Seventeen riggers, millwrights and engineers deployed
-
Safety strategies developed for the inclined ramp and heavy housing
The Outcome
Ram housing replacement completed on time and within budget
The replacement was completed within the three-week deadline and within budget, with production downtime minimised during the project.
- Client: Aluminium manufacturer
- Location: Texas, USA
- Sector: Metals
- Programme: Extrusion press main ram housing replacement
- Timeline: 3 weeks

Aluminium slab casting equipment installation in Belgium
- 40,000+ Project hours
- Lichtervelde, Belgium Location
- Metals & Minerals Sector

Greenfield aluminium plant installation in Kathua, Jammu
- 610 days Programme length
- 230 + 25 supervisors Workforce
- 1,400 tonnes Mill capacity

Mechanical installation for a new cold rolling mill and finishing line
- 6,250+ tonnes Equipment installed
- 375 km Electrical cabling
- 30 microns Baseplate alignment tolerance

Three extrusion press and ASRS installation programme in India
- 3 Extrusion presses
- 7, 8 and 10 inch Press sizes
- 150+ Planned team

4,400-ton extrusion press installation in the Southwest USA
- 4,400 tons Press
- 400 tons Gantry
- R120 forklift + hydraulic press cart Equipment

Production line relocation from Bulgaria to the Netherlands
- 2 Production lines
- furnaces + casting lines + transformers + cooling towers + pumps Main equipment
- cross-Europe Transport

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Automated tyre plant installation in Tangier, Morocco
- 70,560 Planned project hours
- 120 days Duration
- multiple Plant zones
Beck & Pollitzer Industrial Intelligence™