Installing ventilation units, electrical cabinets, glycol coolers, piping, air ducts and evaporators for a multinational food-products company in Krasnodar.

The Challenge
Integrating production equipment, utilities and electrical work within one dairy-plant installation
The Krasnodar project combined machinery handling with several supporting plant systems. The scope covered ventilation units, electrical cabinets and glycol coolers together with pipework, air ducts and evaporators.
Our Solution
Mechanical, electrical and utility installation followed by hydraulic testing
The installation scope brought the equipment and supporting systems together under one programme. Teams installed the ventilation and cooling equipment, electrical cabinets, pipelines, air ducts and evaporators.
Electrical works formed part of the installation, and hydraulic tests were carried out on the completed piping systems.
Ventilation-unit installation |
Electrical-cabinet installation |
Glycol-cooler installation |
Pipeline and air-duct installation |
Evaporator installation |
Electrical works |
Hydraulic testing of piping systems |
Ventilation-unit installation |
Electrical-cabinet installation |
Glycol-cooler installation |
Pipeline and air-duct installation |
Evaporator installation |
Electrical works |
Hydraulic testing of piping systems |
-
Ventilation-unit installation
-
Electrical-cabinet installation
-
Glycol-cooler installation
-
Pipeline and air-duct installation
-
Evaporator installation
-
Electrical works
-
Hydraulic testing of piping systems
The Outcome
Machinery and utility installation completed at the Krasnodar dairy plant
The project was completed with the specified machinery, electrical work and utility systems installed and hydraulic testing included in the delivery scope.
- Client: Multinational food-products company
- Location: Krasnodar, Russia
- Sector: Consumer Goods
- Programme: Dairy plant machinery and services installation

Turnkey hygiene production line installation in France
- 4,500 Project hours
- 2 months Duration
- 232 Containers unloaded

Complex production tank rigging & installation in Poland
- 40 Project hours
- 1 day Duration
- 4 Team size

Coffee roasting plant installation and assembly in Sweden
- 20 On-site specialists
- 1 year Planned programme duration
- Järfälla, Sweden Location

Mechanical and electrical canning line installation in a live plant
- 79 Operatives
- ~60 tons Power and control cable
- ~15 tons Cable routes

Installation of three 28-metre agricultural grain silos in Hungary
- 3 Silos installed
- 28 m Installation height
- 80,000+ Screws used

Autostore installation for a clothing distribution centre in North Carolina
- 1,444 Grid cells
- 36 Robots
- service + overhang mezzanines Systems

Automated cold-store warehouse installation for a dairy producer
- 3 sets Steel structures installed
- 45 specialists + 3 engineering/safety staff Installation team
- <50 mm Crane-to-ceiling clearance

AS/RS installation with 19 aisle cranes in Ohio
- 19 Aisle cranes
- cranes + pallet conveyors Main systems
- zero reported incidents/accidents Safety outcome