Replacing 14 robots and 10 robot bases inside an automotive welding shop, including precision lifts over existing fences and equipment.

The Challenge
Lifting replacement robots over fences and existing welding-shop equipment
The automotive manufacturer required an underbody line replacement covering 14 robots and ten robot bases inside a welding shop. The principal handling challenge was moving the robots over fences and other installed components.
The project also required mechanical and electrical dismantling, replacement positioning and reconnection of services and the exhaust system.
Our Solution
Three forklift configurations used for controlled robot movement and replacement
The 24-person team dismantled the existing equipment, relocated the new robots into position and reconnected the associated services and exhaust system.
Handling equipment included a 5.5-tonne electric Hyster forklift, a VersaLift 40/60 with crane jib and a 7-tonne Hyster forklift with crane jib. Safety planning formed part of the work throughout the 940 project hours.
Mechanical and electrical dismantling |
Replacement of 14 robots and ten robot bases |
Service and exhaust-system connections |
5.5-tonne electric Hyster forklift |
VersaLift 40/60 with crane jib |
7-tonne Hyster forklift with crane jib |
Mechanical and electrical dismantling |
Replacement of 14 robots and ten robot bases |
Service and exhaust-system connections |
5.5-tonne electric Hyster forklift |
VersaLift 40/60 with crane jib |
7-tonne Hyster forklift with crane jib |
-
Mechanical and electrical dismantling
-
Replacement of 14 robots and ten robot bases
-
Service and exhaust-system connections
-
5.5-tonne electric Hyster forklift
-
VersaLift 40/60 with crane jib
-
7-tonne Hyster forklift with crane jib
The Outcome
Underbody line replacement completed on time across 940 project hours
The project was completed on time after 940 project hours using a 24-person team.
- Client: Automotive manufacturer
- Location: Czech Republic
- Sector: Automotive
- Programme: Robotised underbody line replacement

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Automated tyre plant installation in Tangier, Morocco
- 70,560 Planned project hours
- 120 days Duration
- multiple Plant zones

Vulcanisation press relocation from Tunisia to the Czech Republic
- 450 Project hours
- 30 days Duration
- 2 Countries

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

Multi-scope automotive summer shutdown upgrade in Hungary
- 2 weeks Shutdown window
- 20 years of accumulation Legacy cabling removed
- precision levelling and MEWP access Key methods

Nine-robot replacement during an automotive summer shutdown
- 9 Robots replaced
- 20 Team size

Tyre manufacturing plant installation in Tangier, Morocco
- 70,000+ Project hours
- 8+ months Duration
- 5+ km Conveyor systems

24-tonne TEF 220 press installation in the Czech Republic
- 24 tonnes Press weight
- 10 hours Working day
- PT5400 Gantry