24-tonne TEF 220 press installation in the Czech Republic

Unloading and installing a 24-tonne TEF 220 press with mechanical, electrical, air and cooling-water connections using a PT5400 gantry.

Czech Republic

The Challenge

Bringing heavy press handling and service connections together within one installation scope

The automotive technology company required a 24-tonne TEF 220 press to be unloaded, positioned and fully installed, including the associated electrical, compressed-air and cooling-water connections.


Our Solution

PT5400 gantry and 7t forklift used before mechanical, electrical and utility connections

A PT5400 gantry, 7t Hyster forklift, cherry picker and scissor lift were used for unloading and positioning the press.

The installation then covered mechanical and electrical setup together with compressed-air and cooling-water connections. The site team worked ten-hour shifts through the programme.

24-tonne TEF 220 press unloaded and positioned
PT5400 gantry used for heavy handling
7t Hyster forklift, cherry picker and scissor lift deployed
Mechanical installation
Electrical installation
Compressed-air connection
Cooling-water connection
Ten-hour working shifts
24-tonne TEF 220 press unloaded and positioned
PT5400 gantry used for heavy handling
7t Hyster forklift, cherry picker and scissor lift deployed
Mechanical installation
Electrical installation
Compressed-air connection
Cooling-water connection
Ten-hour working shifts
24-tonne TEF 220 press unloaded and positioned
PT5400 gantry used for heavy handling
7t Hyster forklift, cherry picker and scissor lift deployed
Mechanical installation
Electrical installation
Compressed-air connection
Cooling-water connection
Ten-hour working shifts
24-tonne TEF 220 press unloaded and positioned
PT5400 gantry used for heavy handling
7t Hyster forklift, cherry picker and scissor lift deployed
Mechanical installation
Electrical installation
Compressed-air connection
Cooling-water connection
Ten-hour working shifts
  • 24-tonne TEF 220 press unloaded and positioned
  • PT5400 gantry used for heavy handling
  • 7t Hyster forklift, cherry picker and scissor lift deployed
  • Mechanical installation
  • Electrical installation
  • Compressed-air connection
  • Cooling-water connection
  • Ten-hour working shifts

The Outcome

TEF 220 press installed, connected and handed over

The installation was completed on time, including the press setup and specified service connections through to handover.

Press weight
24 tonnes
Working day
10 hours
Gantry
PT5400
Forklift
Hyster 7t
Utilities
air + cooling water
Project Details
  • Client: Automotive technology company
  • Location: Czech Republic
  • Sector: Automotive
  • Programme: TEF 220 press unloading and installation

Related Projects

Beck & Pollitzer Industrial Intelligence™

Industrial insight drawn from real-world delivery. Explore reports, articles and expert perspectives on the challenges shaping modern manufacturing and industrial programmes.
What manufacturers should consider before relocating production →
8 min

What manufacturers should consider before relocating production →

5 min read

What manufacturers should consider before relocating production →

5 min read

Your next project starts here

Whether you’re exploring an opportunity, planning a facility or preparing for installation,
our specialists can help you take the next step with confidence.
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.