Unloading and installing a 24-tonne TEF 220 press with mechanical, electrical, air and cooling-water connections using a PT5400 gantry.

The Challenge
Bringing heavy press handling and service connections together within one installation scope
The automotive technology company required a 24-tonne TEF 220 press to be unloaded, positioned and fully installed, including the associated electrical, compressed-air and cooling-water connections.
Our Solution
PT5400 gantry and 7t forklift used before mechanical, electrical and utility connections
A PT5400 gantry, 7t Hyster forklift, cherry picker and scissor lift were used for unloading and positioning the press.
The installation then covered mechanical and electrical setup together with compressed-air and cooling-water connections. The site team worked ten-hour shifts through the programme.
24-tonne TEF 220 press unloaded and positioned |
PT5400 gantry used for heavy handling |
7t Hyster forklift, cherry picker and scissor lift deployed |
Mechanical installation |
Electrical installation |
Compressed-air connection |
Cooling-water connection |
Ten-hour working shifts |
24-tonne TEF 220 press unloaded and positioned |
PT5400 gantry used for heavy handling |
7t Hyster forklift, cherry picker and scissor lift deployed |
Mechanical installation |
Electrical installation |
Compressed-air connection |
Cooling-water connection |
Ten-hour working shifts |
-
24-tonne TEF 220 press unloaded and positioned
-
PT5400 gantry used for heavy handling
-
7t Hyster forklift, cherry picker and scissor lift deployed
-
Mechanical installation
-
Electrical installation
-
Compressed-air connection
-
Cooling-water connection
-
Ten-hour working shifts
The Outcome
TEF 220 press installed, connected and handed over
The installation was completed on time, including the press setup and specified service connections through to handover.
- Client: Automotive technology company
- Location: Czech Republic
- Sector: Automotive
- Programme: TEF 220 press unloading and installation

HSE consultancy support for a major EV manufacturing facility in Saudi Arabia
- 10 months Programme length
- 100+ RAMS reviewed
- 500+ Observations closed

Automated tyre plant installation in Tangier, Morocco
- 70,560 Planned project hours
- 120 days Duration
- multiple Plant zones

Vulcanisation press relocation from Tunisia to the Czech Republic
- 450 Project hours
- 30 days Duration
- 2 Countries

Body shop installation for a new EV plant in India
- nearly 100 Containers unloaded
- 30 Trucks
- 50 Site team

Multi-scope automotive summer shutdown upgrade in Hungary
- 2 weeks Shutdown window
- 20 years of accumulation Legacy cabling removed
- precision levelling and MEWP access Key methods

Nine-robot replacement during an automotive summer shutdown
- 9 Robots replaced
- 20 Team size

Tyre manufacturing plant installation in Tangier, Morocco
- 70,000+ Project hours
- 8+ months Duration
- 5+ km Conveyor systems

Tier 1 automotive factory installation completed in 60 days
- 120 tonnes Machinery installed
- 60 days Timeline
- unloading + positioning + installation Scope